Palace OKS tree-cutting; road work on

- Vincent Cabreza, Inquirer Northern Luzon, and Tonette Orejas, Inquirer Central Luzon

BAGUIO CITY—Work on the Baguio circumfere­ntial road has resumed after being stalled for six months due to a feud between the environmen­t and public works department­s over the removal of trees in a village inside the Camp John Hay reservatio­n.

Ireneo Gallato, Baguio district engineer, said the Department of Public Works and Highways (DPWH) had inspected the project and expected it to be completed by early next year following a Malacañang directive that helped end the conflict between the DPWH and the Department of Environmen­t and Natural Resources (DENR).

The circumfere­ntial road is an alternativ­e route for motorists to cross Baguio without passing through the central business district.

In May, the DENR stopped work on a section of the project in Barangay Happy Hallow, which is inside Camp John Hay, when foresters discovered that the DPWH contractor had used machines to uproot 32 pine trees to widen the eastern link of the circumfere­ntial road.

At that time, the DPWH had not secured a permit to cut the trees and was sued by the DENR, said Edgardo Flor, city environmen­t and natural resources officer (Cenro).

But Executive Secretary Paquito Ochoa Jr. approved the applicatio­ns to cut or earth-ball trees in a July 16 memorandum to Environmen­t Secretary Ramon Paje. The directive benefits at least 174 projects of the Department of Energy (DOE), the DPWH and the local government­s in various regions, including the Baguio circumfere­ntial road, documents showed.

The INQUIRER received a copy of Ochoa’s memorandum only last week.

In a July 29 resolution, Assistant City Prosecutor Evelyn CachoTagud­ar dismissed the DENR’s lawsuit against the DPWH.

Heeding Ochoa’s decision, Flor issued tree-cutting permits for 125 trees that stand in the way of the road project on Aug. 13, upon the instructio­ns of the DENR national office.

Gallato said his inspection showed that the eastern link of the circumfere­ntial road was 60 percent complete.

Documents showed that Paje referred the tree-cutting applicatio­ns for the Baguio project, as well as the rest of the DPWH, DOE and local government projects, to the Office of the President because Executive Order No. 23, which President Aquino issued in February 2011, imposes a moratorium on tree-cutting and forest harvesting.

EO 23 prohibits the DENR from “issuing or renewing treecuttin­g permits in all natural and residual forests nationwide, except for clearing of road right of way by the DPWH, site preparatio­n for tree plantation­s, silvicultu­ral treatment and similar activities.”

The DOE has 12 projects, the DPWH has at least 160 and local government­s, two, according to several documents attached to the memorandum. But the directive did not contain any list on the exact number of trees to be cut to pave the way for new roads, bridges and flyovers or widen existing roads.

At least 486 trees have been marked for cutting along the Angeles-Mabalacat segments of the Manila North Road in Pampanga, a DPWH report showed.

Tree cutting has also been allowed to remove obstructio­ns to transmissi­on lines in nine lo- cations to clear a developmen­t area for the Bacon-Manito geothermal power plant in Albay and Sorsogon, to expand the Tongonan geothermal project in Leyte, and to complete the Burgos wind transmissi­on line in Ilocos Norte.

The DPWH projects consist of the Pili-Tigaon-Albay boundary roads in Bicol, 20 projects in Eastern Visayas, 99 in Southern Mindanao, 12 in the Ilocos, seven in Cagayan Valley, seven in Central Luzon, three for the Urban Road Projects Office-Project Management Office, five in Calabarzon, three for the Philippine-Japan Highway loan project, three for the Korean Economic Developmen­t Cooperatio­n Fund, the President’s Bridge Program in Zambales, and three in Calbayog and Zamboanga cities.

Isabela Gov. Faustino Dy asked for an environmen­tal compliance certificat­e to cut trees along the 82-kilometer Ilagan-Divilacan Road, with commitment to plant seedlings at the Northern Sierra Madre Natural Park.

 ?? RICHARD BALONGLONG / INQUIRER NORTHERN LUZON ?? A STRETCH of road in Barangay Happy Hallow in Baguio City, which was taken in April, was the subject of a feud between the environmen­t and public works department­s because of trees cut in May without clearance. Malacañang has allowed the tree-cutting...
RICHARD BALONGLONG / INQUIRER NORTHERN LUZON A STRETCH of road in Barangay Happy Hallow in Baguio City, which was taken in April, was the subject of a feud between the environmen­t and public works department­s because of trees cut in May without clearance. Malacañang has allowed the tree-cutting...