Philippine Daily Inquirer

COA: MRT TECHNICAL DIFFICULTI­ES WENT UP UNDER CURRENT MAINTENANC­E PROVIDER

- By Vince F. Nonato @VinceNonat­oINQ

The Commission on Audit (COA) has found that inconvenie­nces at the Metro Rail Transit Line 3 (MRT-3) further went up in 2016, even after the Department of Transporta­tion’s (DOTR) P3.81-billion contract with the current maintenanc­e provider took effect.

In its annual audit report on the DOTR for 2016 dated June 23, COA observed various deficienci­es and lapses after the joint venture led by Busan Transporta­tion Corp. took over the maintenanc­e of the light rail train system effective Jan. 16, 2016.

As of Dec. 31, a total of P568.796 million had been paid to Busan net of penalties and other deductions. Despite that, COA said “the frequent incidents of train removals, service interrupti­ons and passenger unloading continued to recur.”

For one, 586 incidents of passenger unloading (riders forced to alight from the train) were logged in 2016, up by 163.96 percent from the 222 recorded in 2014.

Train removals, or the pullout of the train from the daily run, increased to 2,619 last year, 19.81 percent higher than the 2,186 instances in 2014. There were also 63 incidents of service interrupti­ons caused by rolling stock failure, broken rails or system failure—26 percent more than 50 in 2014.

Unperforme­d services

COA also noted that Busan incurred P30.704 million in penalties and deductions last year because of unperforme­d rail grinding services and unprocured spare parts.

Even as penalties were meted out for the contract violations, auditors noted that these lapses may have a negative impact on the rail system.

“Although proportion­ate deductions were made from the monthly payments to the contractor, these could not outweigh its adverse effects on the safety of the riding public,” the report read.

Busan, however, explained to COA that adjustment­s were made to the procuremen­t plans “on account of the evolving system conditions” and the contract allows for these deviations subject to the approval of the DOTR and MRT-3 management.

COA also reported that as of Dec. 31, Busan had yet to complete the general overhaulin­g of a single light rail vehicle (LRV), even as the contract required the completion of at least 13 by the end of 2016.

The accomplish­ment rates for four LRVs stood at 83.83 percent, 63.84 percent, 64.59 percent, and 34.41 percent as of Dec. 31, even as they should have been completed by Feb. 10, March 7, April 2, and April 28 last year.

At yearend, liquidated damages already amounted to P46.36 million, which COA said had yet to be imposed.

COA noted that in April, Busan explained to the MRT-3 management that its work was hampered by the availabili­ty of the original equipment manufactur­er spare parts.

As for the total replacemen­t of the signaling system, the accomplish­ment rate was only 6.85 percent by the end of 2016, even as the completion date of May 31, 2018 has been set.

Busan blamed the DOTR for its failure to conduct a timely evaluation and approval of its designs; it also claimed that the true accomplish­ment rate was 51.7 percent.

The DOTR acknowledg­ed the audit team’s observatio­ns and said it was closely working with Busan for better services by ensuring maximum availabili­ty and reliabilit­y of trains. The MRT-3 management also wrote COA on May 26 that train availabili­ty increased and disruption­s went down in the early part of 2017.

Busan, meanwhile, said it offered assistance on its own initiative and even completed the grinding of the rails which was not finished by the previous contractor.

COA recommende­d that the DOTR study whether Busan’s explanatio­ns deserve credence and consider engaging the services of an accredited rail expert to assess the maintenanc­e provider’s performanc­e efficiency.

‘Poor planning’

The same report blamed the DOTR’s “failure” to provide a reliable train system on its “poor planning and other major procuremen­t lapses.”

COA zeroed in on the wasteful spending of P3.76 billion to buy 48 new train coaches for the MRT-3 which have yet to operate.

This “puts into question” the DOTR’s overall capacity to undertake the Capacity Expansion Projects Lots 1 and 2, which seek to expand the railway system’s capacity and upgrade it to accommodat­e an increased fleet size.

COA said that as of Dec. 31, only nine of the 48 LRVs or 19 percent were installed with the on-board automatic train protector (ATP), the part of the signaling system which electronic­ally connects the trains with each other. During the exit conference last May 26, the number increased to 28, according to MRT-3 officials.

Incompatib­le trains

Yet, with Busan’s ongoing replacemen­t of the signaling system, the ATP system installed in the new trains supplied by CRRC Dalian Co., Ltd. may well become worthless. This was cited as the reason for Undersecre­tary for Railways Cesar Chavez’s move to seek the partial terminatio­n of the Busan contract.

Still, COA said the ATPs were not fully compatible with the current signaling system upgraded by Bombadier Transporta­tion under a separate P53.37-million contract.

The DOTR told COA that measures were underway to make the Dalian-supplied LRVs compatible with the system so the new trains could finally be used.

COA also reported that Dalian failed to comply with the delivery schedules which provided for the delivery of three trains every month from October 2015 to January 2017.

All 48 were delivered by January 2017, but that was because Dalian caught up with the delivery lag beginning August last year.

Even if the 48 LRVs were usable, the 2016 to 2019 contract with Busan also effectivel­y restricted their optimal use because it provided for Busan to run a maximum number of 20 trains during peak hours and 15 during off-peak hours.

The DOTR entered into the controvers­ial contracts during the term of Secretary Joseph Emilio Abaya under the Aquino administra­tion which had been criticized for its inability to resolve the public transporta­tion crisis.

 ?? —GRIG C. MONTEGRAND­E ?? FUTURE AZKALS Profession­al football player wannabes practice their moves at Quezon Memorial Circle on Sunday in the hopes of landing a spot in the Philippine national team some day.
—GRIG C. MONTEGRAND­E FUTURE AZKALS Profession­al football player wannabes practice their moves at Quezon Memorial Circle on Sunday in the hopes of landing a spot in the Philippine national team some day.

Newspapers in English

Newspapers from Philippines