Solon wants to streamline process for mass housing

-

MANILA – Senator Sonny Angara on Friday pushed for the streamlini­ng and simplifyin­g of the issuance of housingrel­ated clearances and permits through the creation of one-stop processing centers to address the backlog in the constructi­on of settlement­s for the informal sector.

In a statement, Angara warned that the national housing backlog would worsen and turn into a national housing crisis if the bureaucrat­ic red tape in government housing agencies is not reduced.

on future demand and the current pace of production, the backlog in housing units is forecast to hit 6.6 million by 2022, from 5.5 million in 2016.

“But we can ramp up production by improving the regulatory environmen­t. When there is ease in doing business, financing comes in, and with volume comes affordabil­ity,” Angara said.

He said the mandate of several anti-red tape laws should be applied to housing “not just in national government agencies but also in local government­s.”

The senator particular­ly cited Republic Act 10884, which requires the establishm­ent of socialized housing one-stop processing centers.

Angara said building a house is a slog through 27 offices, 78 permits, 156 signatures, 373 documents that could last for months.

For socialized or affordable mass housing, pre-constructi­on processing time could last up to 74 months, if it involves land conversion, titling, and financing, he noted. “Before you pour your first pail of cement, you have to follow a long paper trail. And many families do not have the energy for that,“he said.

Angara said government housing officials have reported to him that it normally takes the National Housing Authority 12 to 30 months to get a green light for constructi­on.

For the Social Housing Finance Corporatio­n, the pre-constructi­on processing time for its Community Mortgage Program projects is between 16 to 74 months.