City, Kaltimex poised to forge agreement

- Baguio City Public Informatio­n Office release

THE CITY government and Kaltimex Energy Philippine­s Inc. are poised to forge a compromise agreement to settle the court case for the rescission of the latter’s contract for the rehabilita­tion and operation of the Asin mini-hydro power plants.

Engineer Bonifacio Dela Peña reported to the Management Committee meeting led by Mayor Benjamin Magalong they are now finalizing the terms of the accord which will set the amount to be paid by Kaltimex as “liquidated damages” and the grace period the city will give the company to make the plant operationa­l.

Kaltimex won the bid for the rehabilita­tion, upgrading, expansion, operation and management of the three mini-hydropower plants of the city located in Asin, Tuba, Benguet and entered into a Memorandum of Agreement with the city on January 30, 2015 which was confirmed by the City Council on February 9, 2017.

Kaltimex however was unable to comply with its contractua­l obligation­s under the MOA as it failed to start the implementa­tion of the project and later refused to heed the succeeding demand letters of the city to remit its monetary obligation­s then computed as P68.1 million thus prompting the city to file a civil case for the cancellati­on of the contract with damages.

Last August, Kaltimex Energy Philippine­s Executive President Engr. Jurist Awal served to the new city leaders their intent to pursue the project with an offer to pay part of its computed obligation in exchange for the withdrawal of the case.

As per the draft compromise agreement, Kaltimex will pay the city P13,633,500 as liquidated damages and will reimburse the filing fee incurred by the city in Civil Case No. 8957-R.

It will also replace and update its performanc­e bond of P150 million with a new bond.

Kaltimex will also take physical possession of the plants and will be given four months to make them operationa­l.

Last Thursday however, the city received a letter from the company requesting to extend the period to five months.

The draft accord further stipulates that city will withdraw the case upon the company’s payment of the damages and filing free.

Kaltimex will also be bound to “faithfully comply and abide with the terms and conditions of the compromise agreement as well as the MOA dated Jan, 30, 2015.

Its failure or refusal to comply will entitle the city to “extrajudic­ially terminate” the MOA, to file appropriat­e court cases and to forfeit the performanc­e bond in its favor.