Sun.Star Cebu

COA to CCMC contractor: no papers, no pay

In its annual audit report for 2016, COA suspended the P90.2 million payment to C.E. Padilla Constructi­on Inc. due to its failure to submit documents

- RVC

The new Cebu City Medical Center (CCMC) is 17.53 percent done but the contractor, CE Padilla Constructi­on Inc., has yet to complete the documentar­y requiremen­ts since it began work in 2015.

It is for this reason that the Commission on Audit (COA) is suspending the payment of P90.2 million for the work done so far by CE Padilla.

The P90.2 million is only a chunk of the P515 million allocated for Phase 1 of the CCMC project. The 10- storey hospital building has a project cost of P1.5 billion.

An audit report for 2016 pointed out the commenceme­nt of constructi­on despite the absence of a building permit, which can only be issued when papers are in order. Why this is so the current bids and awards committee (BAC) said only the former BAC can explain.

Neverthele­ss, the building permit applicatio­n is being processed. One snag in the applicatio­n has something to do with a small lot that CCMC has partly occupied.

The massive CCMC replaces the old one, which had been wrecked down after being found structural­ly unstable after the October 2013 earthquake.

The Commission on Audit (COA) has questioned the P90.2 million payment that Cebu City Government made to the contractor of the new Cebu City Medical Center (CCMC) despite failure to submit some needed documents.

The P90.2 million is the first partial payment representi­ng 17.52 percent work accomplish- ment for the phase 1 of CCMC.

The phase 1 of the project has a contract cost of P514.9 million, which forms part of the P1.5 billion total cost of the entire project.

In its annual audit report for 2016, COA suspended the P90.2 million payment to C.E. Padilla Constructi­on Inc. due to its failure to submit documents, such as certified true copy of the certificat­ion of authority of BF General Insurance Company Inc. issued by the Insurance Commission with the validity period from July 1, 2014 to Dec. 31, 2015.

The contractor only attached a certificat­e of authority that was only valid until 12:00 midnight of June 30, 2015. C.E. Pa- dilla also failed to submit a certified true copy of the building permit that the City issued for the project.

City Engineer Josefa Ylanan said they also noted the same when they made an evaluation of the project sometime in June last year, before Mayor Tomas Osmeña assumed office.

It was then acting mayor Margarita Osmeña who issued the suspension of works for CCMC pending the compliance of contractor on the permit that they need to secure.

The building permit was not processed because the ownership of a portion of the 4,000-square-meter lot on Panganiban St., the site of the 10-story hospital, had yet to be establishe­d that time. It was only in September last year when the contractor complied with the permit.

The project officially started on July 23, 2015 as stated in the statement of work accomplish­ment that the Department of Engineerin­g and Public Works (DEPW) submitted. COA asked the City to direct concern officials and employees to submit the required documents and demand deficienci­es and inconsiste­ncies that they noted.

“I can’t explain for them (previous officials) because I was even the one who rec- ommended the suspension of works for the project for lack of permit. Work on the project is now on track,” Ylanan told SunStar Cebu.

It its comment to COA, the City said the current Bids and Awards Committee (BAC) for Infrastruc­ture and Consulting Services is not privy to the reasons of the previous administra­tion’s failure to comply with the requiremen­ts.

They, however, started to implement remedies to comply with the requiremen­ts mandated under Section 37.1.6 and 37.4.2 of the Revised Implementi­ng Rules and Regulation­s of Republic Act 9184.

“Right now, we’re making sure that the project is well-monitored. I assigned a project engineer there from DEPW who will constantly check the works of the project to make sure that it will be on track,” Ylanan said.

Ylanan said they’re expecting that first four floors of the new hospital will be completed this month as directed by Osmeña.

“The mayor wants that after the constructi­on of the first four floors, it will be operationa­l already and we are trying our best to comply,” she said.

When sought for comment, former Mayor Michael Rama said he has no idea about the payment since the financial aspect of the project concerns the City Treasurer’s Office.

“I don’t get involved in them getting paid. If we paid them, they must sent us a billing because we can’t process payment without it,” he said.

Rama assured that he will inquire former city administra­tor Lucelle Mercado on the matter.

SunStar Cebu tried to get the side of C.E. Padilla but no one is available for an interview.

I can’t explain for them (previous officials) because I was even the one who recommende­d the suspension of works for the project for lack of permit. Work on the project is now on track. CITY ENGINEER JOSEFA YLANAN

 ??  ?? WORK AS USUAL: It’s work as usual for these constructi­on workers who are not aware of the issues concerning the Cebu City Medical Center project. SUN.STAR FOTO / ALEX BADAYOS
WORK AS USUAL: It’s work as usual for these constructi­on workers who are not aware of the issues concerning the Cebu City Medical Center project. SUN.STAR FOTO / ALEX BADAYOS

Newspapers in English

Newspapers from Philippines