DPWH announces near completion of bridge in Bulacan province

- BY REYNALDO G. NAVALES Sun.Star Staff Reporter

“We now wrapping up the constructi­on of the 1.12 kilometer Angat Bridge along the Plaridel Bypass Road”, said Villar.

The Department of Public Works and Highways (DPWH) chief added that even with the challenges brought about by the pandemic, the P1.09 billion project including the constructi­on Bridge No. 9 with a length of 40 meters and one kilometer road paving continues to move forward.

With funding support from the Government of Japan thru the Japan Internatio­nal Cooperatio­n Agency (JICA), the 24 kilometers Plaridel Bypass Road has fully linked on May 2018 the North Luzon Expressway in Barangay Burol, Balagtas and Maharlika Highway in Barangay Maasim, San Rafael, Bulacan.

To fast-track the completion of the bridge project that will complement the widening of Plaridel Bypass Road from two lanes to four lanes, Undersecre­tary for Unified Project Management Office (UPMO) Operations Emil K. Sadain and Project Director Virgilio Castillo of DPWH UPMO Roads Management Cluster 1 held a meeting with JICA Senior Representa­tive Kiyo Kawabuchi, Embassy of Japan in the Philippine­s Second Secretary Tomohiro Matsubara, and the joint venture contractor ShimizuFF Cruz and the project consultant­s to thresh out issues in project implementa­tion.

Sadain reported that in keeping with the target to complete by December 2020, the final concrete pouring of deck slab at end closure between pier 17 and 18 was held on Tuesday, October 20, 2020.

The new Angat Bridge consisting of seven span pre-stressed concrete continuous box girder is being built by balance cantilever method on a bored piles foundation.

This new bridge and the additional two lanes roadway will address the future increase of traffic utilizing the Plaridel Bypass Road as an alternativ­e route to the Maharlika Highway, Sadain said.

With about 15,000 vehicles diverted from the congestion of Maharlika Highway at the town proper of Plaridel, Pulilan, and Baliuag some section of Plaridel Bypass Road during late afternoon up to night time have already shows traffic build-up.

LARK FREEPORT --- Public Works and High ways Secretary Mark A. Villar announced that a new two-lane bridge across Angat River in Bustos, Bulacan is about to be completed.