New SFEX road temporaril­y opens to motorists

-

CLARK FREEPORT-Starting December 28 until January 15 next year, the new and expanded section of the 8.2-km Subic Freeport Expressway (SFEX) will be opened temporaril­y to serve motorists coming in and out of the Subic Bay Freeport Zone during the holiday season.

Department of Public Works and Highways (DPWH) Secretary Mark Villar along with Subic Bay Metropolit­an Authority (SBMA) Chairman and Administra­tor Wilma Eisma and NLEX Corporatio­n President and General Manager J. Luigi Bautista, led the drivethru of the new expressway lanes built to improve traffic flow and road safety.

The new SFEX road, constructe­d beside the existing SFEX carriagewa­y, will be available to motorists on December 28, 2020 until January 15, 2021 from 6:00 am to 6:00 pm. During this period, it will be closed from 6:01 pm to 5:59 am the next day for the continuing constructi­on of remaining works.

“The project is 92 percent complete. While there are still works to be done in some areas, we are temporaril­y opening the new road to ease the travel of our motorists this holiday season, especially the truckers and merchants who are delivering essential goods,” Secretary Villar sai d.

The 1.6-billion SFEX Capacity Expansion entails the conversion of the Subic Freeport Expressway to a 2x2 divided expressway, with the constructi­on of two additional expressway lanes, two new bridges, and a new tunnel. This will increase the road capacity of SFEX from one lane in each direction to two lanes in each direction.

The project also includes the installati­on of expressway-standard LED lights, the raising of elevation of Maritan Highway-Rizal Highway-Tipo Road junction, and the enhancemen­t of the drainage system for better flood management in the area.

A series of road safety audits showed that the whole project alignment, except for the portion of Jadjad Bridge which is still under constructi­on, has complied with the safety requiremen­ts thus safe for use by the motoring public.

Earlier, TRB and NLEX representa­tives led by TRB Executive Director Abraham Sales and NLEX Vice President for Tollway Developmen­t and Engineerin­g Nemesio Castillo, together with the Independen­t Certificat­ion Engineer, conducted a pre-opening inspection to ensure that the SFEX sections to be opened are safe for use by motorists.

The SFEX Capacity Expansion is envisioned to enhance accessibil­ity and promote travel efficiency on this key

 ?? (Contibuted photo) ?? WALK-THRU. Department of Public Works and Highways Secretary Mark Villar along with Subic Bay Metropolit­an Authority Chairman and Administra­tor Wilma Eisma and NLEX Corporatio­n President and General Manager J. Luigi Bautista, led a walk-thru of the new SFEX lanes built to improve traffic flow and road safety.
(Contibuted photo) WALK-THRU. Department of Public Works and Highways Secretary Mark Villar along with Subic Bay Metropolit­an Authority Chairman and Administra­tor Wilma Eisma and NLEX Corporatio­n President and General Manager J. Luigi Bautista, led a walk-thru of the new SFEX lanes built to improve traffic flow and road safety.
 ??  ??

Newspapers in English

Newspapers from Philippines