Sun.Star Pampanga

DPWH speeds up Bulacan Road Expansion Project

-

MALOLOS CITY -- The Department of Public Works and Highways (DPWH) has fast tracked the ongoing expansion works at the 24.61 kilometer-Arterial Road Bypass in Bulacan.

With an overall accomplish­ment of 47.8 percent, DPWH is trying to move forward as quickly as possible to accelerate delivery of the widening from two to four lanes the entire alignment of Plaridel Bypass Road for the highway to keep up with the increasing number of veh i cl es.

“The road expansion project will address traffic woes of motoring public triggered by steady growth in number of vehicles including heavy trucks using the bypass road as alternate route to Daang Maharlika Highway,” DPWH Undersecre­tary Emil Sadain explained.

“Funded by the Government of the Philippine­s and Government of Japan through Japan Internatio­nal Cooperatio­n Agency Loan Agreement No. PH-P266 financing, the Arterial Bypass Road Project Phase 3 as the final stage has enough road right of way space for additional two lanes since this was considered during the original planning and design phases,” he added.

The arterial road alignment traverses five municipali­ties namely Balagtas, Guiguinto, Plaridel, Bustos and San Rafael bypassing the perennial traffic congestion at the core urban areas along Philippine­s - Japan Friendship Highway also called Maharlika Highway road section of Plaridel, Pulilan and Baliuag to San Rafael.

Widening of the first 2.22-kilometer section of Arterial Plaridel Bypass Road including one of Luzon’s longest bridge across Angat River in Bustos, Bulacan under Contract Package 3 was earlier completed in the first quarter of 2021.

Presently ongoing at 43 pecent is Contract Package 4 from Sta. 49+ 625 in Bustos to Sta. 57+ 365.73 in San Rafael awarded to Sino Road & Bridge Group Co., Ltd.

This section, targeted for completion by January 2023, involves constructi­on of 7.38 kilometer additional two lanes of portland concrete cement pavement (PCCP) road, a 36.86 meter-single span pre-stressed concrete deck girder bridge, 7 at-grade intersecti­ons, a 318.55 meter flyover at intersecti­on, widening of drainage, slope protection and miscellane­ous works.

Meanwhile, constructi­on of additional two lanes for Contract Packages 1 and 2 from Sta. 34+ 900 in Burol, Balagtas to Sta. 47+ 400 in Bustos is also ongoing under contract with CM Pancho Constructi­on, Inc.

These contract packages which was rolled-out in the first quarter of 2021 covers the PCCP of additional 2 lanes for the 11.82 kilometer-road with carriagewa­y width of 7 meters, constructi­on of seven short bridges with a total length of 260.62 meters, 2 overpass/ flyovers, extension of 10 reinforced concrete box underpass for farm equipment and animal crossing, 16 at-grade intersecti­ons, drainage, slope protection and other miscellane­ous works. (PIA 3)