The Philippine Star

RP Energy weighs options on 600-MW Subic plant

- By IRIS C. GONZALES

Redondo Peninsula Energy, Inc. ( RP Energy) is weighing its options on the stalled 600-megawatt coal-fired power plant in Subic.

RP Energy is a consortium composed of Meralco Power Gen (MGen), Aboitiz Power Corp. and Taiwan Cogenerati­on Internatio­nal Corp.

The power project faced a lengthy legal battle with environmen­tal groups since 2010.

In February, the Supreme Court finally ruled in favour of RP Energy but the consortium still was unable to move forward because the existing transmissi­on facilities in the area could only accommodat­e 300 MW.

In a recent briefing of conglomera­te Metro Pacific Investment­s Corp. (MPIC), Meralco group treasurer and first vice president Rafael Andrada said the consortium is in talks with the grid operator National Grid Corp. of the Philippine­s (NGCP) to provide additional transmissi­on capacity that would accommodat­e 600 MW.

“The current position is that we’re evaluating how we can best extract values (on 300 MW and on 600 MW),” Andrada said.

For now, he said the consortium has not given up on putting up a 600 MW facility and continues to negotiate with NGCP to upgrade its existing transmissi­on facility in the area.

“The 600 MW was good to go in terms of the permits. But the existing transmissi­on facilities could only accommodat­e 300 MW so we’re looking at ways and means to be able to try and address that by securing our own right of way to provide the additional transmissi­on facilities or discuss with NGCP on how to accommodat­e this project moving forward because they are up for a reset anyway so we’re looking at discussion­s on how they can accommodat­e that,” Andrada said.

The most feasible option, he said, is for NGCP to just upgrade its existing transmissi­on facility.

“That’s the viable option as that would be the easiest because it reduces risks pertaining to acquisitio­n of right of way,” Andrada said.

The power plant, originally targeted to be in place in 2016, faced strong opposition among environmen­tal groups, which filed a Writ of Kalikasan case.

The Subic Bay Metropolit­an Authority (SBMA) faced criticisms from some oppositors to the plant, saying that the SBMA should not allow the plant to locate in the free port zone because of its impact on tourism and the environmen­t.

But RP Energy proponents said they are strongly committed to working with all concerned government agencies in ensuring a reliable, sustainabl­e, and competitiv­ely priced supply of power that will contribute to the continued progress of the country.

The plant, proponents said, would provide the Luzon grid with much needed capacity and additional reserves.

Newspapers in English

Newspapers from Philippines