The Philippine Star

Aboitiz Power on shutdown to improve supply in VisMin

- — Danessa Rivera

A power plant of Aboitiz Power Corp. in Mindanao and of Energy Developmen­t Corp. (EDC) in Visayas went on maintenanc­e shutdown to improve their reliabilit­y to supply power to the Visayas and Mindanao grids.

AboitizPow­er disclosed yesterday Unit 1 of the 2x150megaw­att (MW) Davao coalfired power plant of its subsidiary Therma South Inc. ( TSI) started its scheduled shutdown yesterday for preventive maintenanc­e activities.

“This maintenanc­e activity is necessary to review Unit 1 and to implement some corrective measures as needed which should be similar in nature to the coverage of work done in the recently planned outage of Unit 2 from June 18 to July 13,” TSI president and COO Sebastian Lacson said.

The maintenanc­e activity is estimated to last until Sept. 7.

“We are confident that after this outage, TSI should be better equipped to reliably meet the needs of our customers. As always, we will try our best to keep the duration of this interrupti­on to a minimum,” Lacson said.

Originally scheduled to start Aug. 6, AboitizPow­er said the Unit 1 maintenanc­e schedule was moved to Aug. 22 to better adjust to the grid situation.

TSI is coordinati­ng with electric cooperativ­es and distributi­on utilities customers in Mindanao in order to implement measures to mitigate the impact of the maintenanc­e activity.

In another disclosure, EDC said its 77-MW Malitbog Unit 2 Power Plant in Leyte tripped last Aug. 17 after it “experience­d a flashover inside the high voltage terminal box.”

The plant tripping did not cause any supply shortfall in Visayas since the facility was offline and was in the process of testing and commission­ing of its Automatic Voltage Regulator (AVR) under the supervisio­n of ABB, the manufactur­er of the AVR, as part of a 30 day scheduled maintenanc­e outage.

“The incident did not have any impact on the grid as Malitbog Unit 2 was not synchroniz­ed to the grid at that time, and no injuries were sustained by any of the personnel involved,” it said.

Together with ABB and other consultant­s and contractor­s, EDC said it is currently conducting an assessment of the extent of the repairs needed and a full review to determine all contributi­ng factors that led to the plant incident to ensure appropriat­e measures are taken to enable the safe and reliable operation of the unit.

Newspapers in English

Newspapers from Philippines