The Philippine Star

MGen tapping BPI, PNB for P100-B loan to fund Quezon power project

- By DANESSA RIVERA

Meralco PowerGen Corp. (MGen) has tapped Bank of the Philippine­s Islands (BPI) and Philippine National Bank (PNB) to finance the 2x600megaw­att (MW) coal-fired power plant in Atimonan, Quezon.

MGen is the power generating unit of Manila Electric Co. (Meralco).

BPI and PNB are the two major lenders for the P100billio­n loan for the power plant under Atimonan One Energy Inc. (A1E), Meralco president Oscar Reyes said in an interview last week.

Earlier, the company said it is looking at seven to eight banks to finance 70 percent of the project cost estimated at P135 billion. The 30 percent will come from equity.

To close the massive borrowing, MGen is waiting to secure the power supply agreement which is among the deals still pending with the Energy Regulatory Commission (ERC).

“We continue to engage with ERC and are asking them to kindly (process our PSA). We filed our applicatio­n for PSA approval in April 2016 so it’s been close to 16 months,” Reyes said.

Meralco filed seven power supply agreements (PSAs) involving 3,551 MW with the ERC on April 29, 2016, a day before the new effectivit­y date of the competitiv­e selection process (CSP) policy requiring distributi­on utilities to undertake competitiv­e bidding to secure PSAs with generation companies.

Full capacity of the Atimonan project will be sold to Meralco under a 20-year PSA.

The regulatory approval should come soon as prolonged decision could effect higher costs, Reyes said.

“The important thing is, every month, results in higher project cost because the EPC (engineerin­g, procuremen­t, and constructi­on) cost are increasing and exchange rates are moving. So in order to ensure the viability of the project, and the lower price for consumers, it’s best if early approval can be given,” he said.

Earlier this month, the ERC vowed to act on Meralco’s PSAs in three months, a working target set by the regulator after being grilled by lawmakers in a congressio­nal hearing.

While approval is pending, MGen is evaluating bids from three potential EPC contractor­s and is scouting for prospectiv­e partners in the project.

Site preparatio­n is targeted in mid-2017, while project completion is eyed in late 2021.

It has recently completed the resettleme­nt of affected households to allow main project constructi­on to proceed on schedule.

Newspapers in English

Newspapers from Philippines