NGCP upgrading Negros–Panay interconne­ction

- By DANESSA RIVERA

The National Grid Corp. of the Philippine­s (NGCP) will upgrade the capacity of the Negros-Panay interconne­ction to accommodat­e 300 megawatts (MW) by the first quarter of 2018, addressing issues on excess supply in Negros province.

The project will also provide a more reliable connection between two of the major Visayas islands, it said.

The Negros-Panay submarine cable forms part of Stage 1 of the company’s Cebu-Negros-Panay (CNP) 230-kilovolt (kV) backbone project, designed to boost energy stability in the region.

“With the influx of power sources in Negros, CNP Stage 1 will maximize the power generated by variable renewable energy plants in the province,” NGCP said.

NGCP is referring to the sudden increase of the installati­on target for renewable energy facilities from 50 MW to 500 MW for solar and from 200 MW to 400 MW for wind in 2014.

“NGCP’s mandate is to build connection­s to any energy source which wants to sell power through the country’s power backbone. It is imperative that transmissi­on projects are synchroniz­ed with generation projects, so we can ensure that any power that may be generated will be dispatched through the grid,” the company said.

Aside from the submarine cable, other segments of CNP Stage 1 include the double circuit Bacolod-E.B. Magalona overhead transmissi­on line, and the expansion of the Bacolod and Barotac Viejo Substation­s and the E.B. Magalona Cable Terminal Station.

After completing the first phase, NGCP will be able to provide an additional transmissi­on capacity of 210 MW between Negros and Panay Islands and improve voltage levels of major substation­s in Negros Island.

“NGCP’s goals are always centered on increasing the grid’s reliabilit­y and security. With these improvemen­ts to the Visayas grid, we are taking another big step towards ensuring the stability of energy supply for our customers,” the company said.

Applicatio­ns for the implementa­tion of Stages 2 and 3 of the CNP project were filed with the ERC last 2016, with Stage 3 approved last Sept. 4.

CNP Phase 2 is the Magdugo-Cebu transmissi­on line while Phase 3 is the CebuNegros submarine cable and transmissi­on line.