Meralco seeks OK of P60 M capex for Urdaneta substation

- By DANESSA RIVERA

Manila Electric Co. (Meralco) is seeking clearance to spend P60 million to replace a defective transforme­r in its Urdaneta substation to prevent massive power interrupti­on in Makati City.

Meralco filed an applicatio­n with the Energy Regulatory Commission (ERC) for an emergency capital expenditur­e of P60.27 million to replace a power transforme­r in Urdaneta substation.

Meralco needs to apply for ERC approval since the said project is not covered by the capital expenditur­e applicatio­n it applied previously.

The cost will cover the replacemen­t of the defective power transforme­r with a new 83 MVA power transforme­r “in order to avert the prolonged and widespread power interrupti­ons that would affect customers in the cities of Makati and Taguig.”

The replacemen­t was needed after the affected trans- former tripped due to fire in August 2017. Tests showed the transforme­r was no longer safe to be energized.

Meralco transferre­d the load to an adjacent power transforme­r bank which is now operating above critical level at 73 percent.

“The critical loading of the power transforme­r may result to an outage and prolonged and massive interrupti­on in the affected areas,” it said,

Meralco said customers that will be adversely affected include Enderun Colleges and Bonifacio Water Corp., among others, in Taguig City.

Supply will also be adversely affected to major businesses and establishm­ents like Ayala Land Inc., Citi Tower Condominiu­m Corp., Citi Center Condominiu­m Corp., PLDT Inc. The World Centre Condominiu­m, Makati Shangrila Hotel, Department of Trade and Industry and Asian Institute of Management in Makati.