The Philippine Star

More power outages loom until August

- By DANESSA RIVERA

The Department of Energy (DOE) was directed by the Senate yesterday to convene a task force to find an immediate solution to the projected power supply shortage this month until early August this year.

Sen. Sherwin Gatchalian, who chairs the Senate committee on energy, called on the DOE to convene a task force to address these imminent brownouts in the critical weeks until the first week of August.

“Next week until week 31, the possibilit­y of brownouts

is there. We need to prepare, our local government units, ourselves,” he said during the DOE’s presentati­on at the Senate committee hearing.

The DOE told the Senate that it projects severe supply shortage beginning next week until the first week of August due to the extended plant outage of several power plants coupled with the scheduled plant maintenanc­e of some plants in those weeks.

The Luzon power grid could be placed on yellow and red alerts during this time, leading to possible rotational brownouts.

A yellow alert means there are not enough reserves to cover the largest running generating unit at the time but does not necessaril­y lead to power outages. On the other hand, a red alert means there is severe power deficiency which could lead to rotational power interrupti­ons.

“We need to take this seriously,” Gatchalian said. “Data is showing [brownouts] might happen. The possibilit­y is high. I urge the DOE to convene a preventive task force to come up with a plan and submit to this committee the plan as early as next week Monday.”

As a stop gap measure, the DOE said it will urge large power consumers to participat­e in the interrupti­ble load program (ILP) to lessen demand in the power grid.

“For the thinning reserves for the coming weeks, we are going to call on the ILP to make sure there will be lesser demand from commercial establishm­ents,” Energy Secretary Alfonso Cusi said.

Cusi is also pushing for the delay in some maintenanc­e schedules of power plants and the operation of GNPower Dinginin (GNPD) during the critical weeks.

KEPCO Ilijan Corp., which operates the 600-megawatt (MW) Ilijan Block A gas fired power plant, has indicated its readiness to delay further its scheduled maintenanc­e shutdown to end-July.

“Originally, we postponed our maintenanc­e schedule from May 8 to June 24 to sustain our grid capability. As of now, we can delay around one week until July 30, we can delay,” KEPCO Ilijan representa­tive Bumki Park said during the hearing.

Meanwhile, GNPD vice president Bobet Racelis said the first 668-MW unit of coal plant can resume commission­ing and testing in the first week of July, providing enough buffer to the Luzon grid.

Newspapers in English

Newspapers from Philippines