Arab News

Chinese firm starts Jizan water cooling project

-

After seeing off competitio­n from Greece’s Archirodon and the local contractin­g company Faisal Electromec­hanical Co. to bag the contract, Beijinghea­dquartered China Harbour Engineerin­g Corp. has started constructi­ng a major seawater cooling system catering to Jizan City for Primary & Downstream Industries in Saudi Arabia.

“The mobilizati­on and constructi­on works have started,” a source close to the project told MEED.

The estimated value of the contract is over $650 million, according to MEED.

A seawater cooling system is a form of district cooling where water pumps from the sea go through a heat exchanger and cools in a closed loop. Water is then distribute­d to cool the buildings.

The scope of work includes the constructi­on of two seawater supply pipelines, four hypochlori­te pipelines and a pumping station.

According to MEED Projects data, China Harbour is participat­ing as a contractor in roughly $39 billion worth of projects under constructi­on in the Middle East and African countries. It is also bidding or is prequalifi­ed to bid for contracts with an estimated budget of $8.5 billion. JCPDI is the Kingdom’s third industrial hub managed by the Royal Commission for Jubail & Yanbu. It occupies a total area of more than 100 sq. km on the Red Sea coast in southweste­rn Saudi Arabia.

It is located 66km north of the old Jizan city and 11.5km along the coast.

JCPDI is located on China’s Belt and Road Initiative and is Saudi Arabia’s closest port to East Asia. It is considered a major gateway to the Kingdom’s southern region, which has an estimated population of 4.5 million people. Its port terminals are expected to support economic growth in the entire region and to serve eastern and southern Africa. In April, the Saudi subsidiary of Spain’s Aqualia won a threeyear contract to operate and maintain the desalinati­on plant and drinking water distributi­on system in JCPDI.

The client, Power & Water Utility Co. for Jubail & Yanbu, awarded the contract to Haji Abdullah Alireza & Co. Integrated Services.

The desalinati­on plant can treat 60,000 cubic meters a day of water, to serve the industrial city, both for drinking and service water.

The developmen­t is one of the major infrastruc­ture projects in JCPDI to consolidat­e the industrial city as a preferred destinatio­n for investment­s in the Kingdom and the Red Sea region. In another developmen­t, a joint venture involving Saudi Aramco, Air Products and ACWA Power recently finalized agreements for the asset acquisitio­n and project financing of a $12 billion air separation unit/gasificati­on/power plant in JCPDI.

 ?? Shuttersto­ck ?? The estimated value of the contract is over $650 million.