Business Day

No more steep tariff hikes for Eskom

- Hilary Joffe Writer at Large

The electricit­y regulator has delivered a strong signal to Eskom that it is not open to steep tariff increases in future and that the power utility must look at shutting inefficien­t power stations and cutting its head count and capital spending to tailor its cost base to lower sales volumes.

The National Energy Regulator of SA (Nersa), which in midDecembe­r granted Eskom a 5.2% tariff increase for 2018-19 instead of the 19.9% Eskom had applied for, has published the reasons for its decision on the tariffs on its website, painting a picture of inefficien­cy, inaccurate forecastin­g and cost overruns at Eskom.

Eskom’s most recent fiveyear multiyear price determinat­ion from Nersa (MYPD3) expires on March 31 and the power utility was supposed to submit an applicatio­n for a further five-year determinat­ion, but in 2016 asked Nersa for a one-year interim tariff increase, ahead of the five-year applicatio­n, which must be submitted later in 2018.

Eskom has also put in regulatory clearing account applicatio­ns totalling R60bn to cover it for lower-than-expected sales and higher-than-expected costs during the middle three years of the MYPD3 period, which, if Nersa granted them, would mean extra revenue in coming years. But Nersa’s stern response to the one-year applicatio­n suggests it will be less than forgiving of the regulatory clearing account applicatio­ns.

Eskom’s tariff troubles contribute­d to the liquidity crisis it faced when investors and bankers withdrew from lending to the utility after its auditors qualified its 2016-17 financial statements last July.

The installati­on of a credible new board and acting CEO in February helped to reassure lenders, with Eskom announcing on February 28 that it had raised R20bn in short-term credit from a syndicate of seven local and internatio­nal banks.

Analysts have cautioned that Eskom will need a thorough restructur­ing of its business model if it is to be sustainabl­e.

In its reasons for its decision, Nersa warns of a “utility death spiral”, saying Eskom’s continued increase in tariffs has caused lower electricit­y consumptio­n, leading to a vicious cycle in which the utility has been trying to recover the same costs from a shrinking customer base, prompting further demands for tariff increases.

“In order to break the vicious

cycle, Eskom needs to reduce its costs (including its fixed-cost base) … while growing its sales,” Nersa stated.

It pointed to a consistent trend of Eskom overestima­ting its sales volumes and made it clear that with an conservati­vely estimated 4,000MW of surplus generating capacity in 2018, Eskom must look at shutting down its most expensive coalfired station, Arnot.

Eskom has already stopped making use of some units at Hendrina, another of its old power stations.

In its tariff determinat­ion, Nersa slashed R20bn off the amount that Eskom had requested for primary energy costs, including R10bn off its coal costs, with benchmarks for coal pricing indicating that the increase in Eskom’s coal costs during the MYPD3 period had been too high. Eskom had also included in its applicatio­n the costs of renewable energy producers with whom it has not yet signed power purchasing agreements.

Nersa cut R11bn off the revenue that Eskom had applied for to cover its operating costs, reducing the sums allowed for staff and maintenanc­e costs as well as for corporate overheads. Nersa said its own benchmarki­ng study had found that Eskom had more than 6,000 excess employees, at an extra cost of R3.8bn.

It noted that Eskom had overspent an average 44% on incentive bonuses over the MYPD3 period, relative to what Nersa had allowed, despite declining sales and low profits.

“In reaching its decision, Nersa considered Eskom’s unwillingn­ess to implement stringent measures to contain its costs,” the regulator said.

“In the light of this, Nersa has adjusted expenditur­e taking this into considerat­ion.”

The regulator also took a close look at the cost overruns in Eskom’s new build programme and disallowed the entire R72bn of historical cost overruns incurred during the MYPD3 period, based on internatio­nal cost benchmarks.

“These costs were tested for efficiency and prudency and it was concluded that they were inefficien­tly incurred,” said Nersa, though it would allow Eskom to try to prove to it that the overruns were prudent.

Nersa had calculated that the 19.9% tariff increase that Eskom had asked for would have added 1.5 percentage points to consumer price inflation and would have reduced the economic growth rate by 0.35 percentage points.