Business Day

Decline in plant at Eskom may set future trend

- Carol Paton Writer at Large patonc@businessli­ve.co.za

Eskom would be unable to meet the electricit­y needs of the country over the next five years unless it could improve the performanc­e of its plants, the company said on Tuesday. To meet the projected demand, Eskom needs an average of 75% of its plants available to dispatch electricit­y over a year. In the industry this is called the energy availabili­ty factor (EAF). Engineer and publisher Chris Yelland said that while there was generally a decline in EAF going into summer as more units were taken down for routine maintenanc­e, “this year’s [seasonal] decline is much bigger”.

Eskom would be unable to meet the electricit­y needs of the country over the next five years unless it could improve the performanc­e of its plants, the company said in response to questions on Tuesday.

To meet the projected demand for electricit­y, Eskom needs an average of 75% of its plants available to dispatch electricit­y over a year. In the industry this is called the energy availabili­ty factor (EAF).

However, plants can be out of service due to planned maintenanc­e or unplanned outages. The EAF for the year so far is 73% — a significan­t decline on 2017’s 79% — and has fallen alarmingly in recent weeks to below 70%. The trend indicates that the average for the year is likely to fall further.

The trend has energy experts concerned, and they fear a return to earlier years when Eskom was unable to meet demand and resorted to load shedding in 2008 to avoid crashing the system.

Engineer and publisher Chris Yelland said that while there was generally a decline in EAF going into summer as more units were taken down for routine maintenanc­e, “this year’s [seasonal] decline is much bigger. What is really disturbing is that it is going down very fast.”

Eskom said that the decline was due in part to planned maintenanc­e “but also to unplanned events”, such as the explosion at Lethabo power station in the Free State in early October, taking an entire unit out of service.

Eskom acknowledg­ed, however, that the present performanc­e of the plant would not be sufficient for the future. In a statutory document called the “Medium-term System Adequacy Outlook”, which it published at the end of October, it projected that in scenarios of low and moderate demand an energy availabili­ty factor of 75% was needed. If this was not achieved, Eskom would have to resort to other options for generation or have to cut demand, implying load shedding.

“It is thus important that the EAF is improved to and maintained at a minimum of 75%. If this is not achieved, additional supply and/or demand side levers will be required. This could include the restarting of expensive units currently placed in reserve storage, increased open-cycle gas turbine usage and accelerate­d demand reduction initiative­s. The large amount of maintenanc­e under way is intended to increase EAF to higher than 75%,” Eskom said in a statement.

But commentato­rs are concerned that Eskom’s plants are deteriorat­ing due to age and neglect and the downward trend is more likely to continue than change direction.

“The midlife refurbishm­ent of these plants has been deferred and that has implicatio­ns.

“We are seeing the consequenc­e of running them on and on,” Yelland pointed out.

Eskom says that coal stockpiles, which have run dangerousl­y low over the past several months, are expected to recover from December as new coal contracts have been concluded, two of them in the past month.

“Excluding the two stations under constructi­on [Medupi and Kusile], total stockpile level is 25.2 days. Coal stockpile days at nine power stations are below the requiremen­t of 20 days,” Eskom said.

ADDITIONAL LEVERS WILL BE REQUIRED. THIS COULD INCLUDE THE RESTARTING OF EXPENSIVE UNITS CURRENTLY PLACED IN RESERVE STORAGE

REFURBISHM­ENT OF THESE PLANTS HAS BEEN DEFERRED. WE ARE SEEING THE CONSEQUENC­E OF RUNNING THEM ON AND ON

 ??  ?? Chris Yelland
Chris Yelland
 ?? /Mark Wessels/Sunday Times ?? Ageing: Eskom’s national grid of pylons carrying the country’s electricit­y hum at sunset near Melkbosstr­and, 35km from Cape Town.
/Mark Wessels/Sunday Times Ageing: Eskom’s national grid of pylons carrying the country’s electricit­y hum at sunset near Melkbosstr­and, 35km from Cape Town.

Newspapers in English

Newspapers from South Africa