Business Day

Claim from Ghana hits Group Five

- Siseko Njobeni Industrial Writer njobenis@businessli­ve.co.za

Group Five and Cenpower Generation are heading for a legal showdown after the Ghanaian firm slapped the constructi­on company with a $60.5m claim to complete a delayed power project.

Group Five and Cenpower Generation are heading for a legal showdown after the Ghanaian firm slapped the constructi­on company with a $60.5m claim to complete a delayed power project. Cenpower’s latest claim, on top of $62.5m the firm has already received for project delays, further pins the cashstrapp­ed Group Five against the wall as woes associated with the Ghana project pile up.

The latest news sent Group Five’s shares into a freefall, as they slumped as much as 67.7% to an all-time low of 11c in early trade on Thursday. It recovered to close 26.5% down at 25c.

Cenpower Generation is a special purpose vehicle created to develop the Kpone independen­t power plant in the Tema industrial zone, close to Ghana’s capital, Accra.

In 2014, Cenpower awarded Group Five the contract to design and construct the Kpone plant. The two companies have been at loggerhead­s over significan­t delays in the project, initially due to come on stream in October 2017. On November 30, the companies announced the terminatio­n of the contract, in which Group Five has already suffered immense losses.

For the 2018 financial year, the loss on Kpone amounts to R1.3bn. In the latest turn of events, Group Five said on Thursday Cenpower has made a claim for $60.5m to cover costs to complete the project. Group Five disputes the claim.

“[Group Five] is in discussion­s with its legal advisers and senior counsel, as well as its bank guarantee providers, with regards to the claim and is considerin­g the available legal action,” it said.

In its statement on the terminatio­n of the contract on November 30, Cenpower CEO Theophilus Sackey hinted at further claims, saying the $62.7m received for the delays “does not come close to the losses suffered by the company”.

Group Five said in terms of the contract any amount it is liable to has to either be agreed between the two companies or determined through the contract’s dispute mechanism.

“This demand has not been independen­tly determined and does not reflect the countercla­ims [Group Five] is legally entitled to and is pursuing,” it said, referring to its own claims against Cenpower. These include claiming back the $62.7m it has paid for delays.

“[Group Five] strongly disputes the amount claimed and the demand for its payment, as the client themselves confirmed that the constructi­on on the plant was complete, with only testing and commission­ing to be performed,” it said.

In its statement, Cenpower said constructi­on of the plant is complete “but testing and commission­ing work still remain to be performed”. It said a technical team has been assembled to complete the outstandin­g commission­ing work as soon as possible. Group Five has maintained Cenpower is responsibl­e for the testing and commission­ing delays, blaming faulty fuel it had provided.

“As communicat­ed, the provision of the fuel was the client’s responsibi­lity and [Group Five] was unable to complete the testing and commission­ing of the plant as the fuel provided by the client was contaminat­ed and unfit for purpose.”

Three independen­t parties and laboratori­es confirmed that the fuel had been contaminat­ed at Cenpower’s source of supply.

“The contaminat­ion of the fuel remained unresolved at the date of terminatio­n,” Group Five said.

CENPOWER WANTS GROUP FIVE TO COVER COSTS TO COMPLETE THE KPONE POWER PROJECT IN GHANA

 ??  ??

Newspapers in English

Newspapers from South Africa