New power capacity stuck in red tape

• Process will delay capacity coming on line for years

- Carol Paton Editor at Large patonc@businessli­ve.co.za

The short-term emergency measures to procure more electricit­y generation capacity that President Cyril Ramaphosa promised last December have become ensnarled in red tape.

It will be years rather than months before new capacity comes on line.

The latest roadblock is the National Energy Regulator of SA (Nersa), which must “concur” with a determinat­ion under the Electricit­y Regulation Act issued by minerals & energy minister Gwede Mantashe before the procuremen­t can begin.

Nersa said on Wednesday that it would take another three months for it to be in a position to concur on short-term measures outlined in the first determinat­ion and another six before it could concur on a second determinat­ion for a range of technologi­es from independen­t power producers. This was because it had to allow for a publicpart­icipation process before it could concur. In April 2017, the high court in Cape Town struck down a department of energy determinat­ion to procure nuclear power on the basis that there had not been public consultati­on.

Once this has happened, the department of mineral resources & energy can issue a request for proposals, which in a competitiv­e process typically takes six months.

Successful projects usually take as long as a year to achieve financial close, which requires all contractin­g with Eskom to be done before financing can be secured.

Industry sources say that a likely scenario then is that constructi­on will begin in 2022.

Solar PV can take 12 to 18 months to build, wind 18 to 24 months, gas about five years and coal about seven years, assuming finance is available.

Before reaching Nersa on February 21, the determinat­ions made by Mantashe had already followed a tortuous process. The department of energy first said in October 2019 that it would procure “emergency” shortterm capacity. It was only after stage 6 load-shedding in December and Ramaphosa’s interventi­on that the department issued a request for proposals.

However, it took another two months after that for Mantashe to take the first regulatory step and draft the two determinat­ions. Commentato­rs have been

NOW THEY’VE ISSUED AN UNNECESSAR­ILY COMPLICATE­D CONSULTATI­ON DOCUMENT, AND REQUIRE COMMENTS ONLY BY MAY 7 2020

critical of the time Nersa says it requires for the consultati­on.

In discussion papers prepared for the consultati­on, Nersa calls on the public to provide views on a wide range of things, many being policy questions long since decided by the Integrated Resource Plan, itself a document of extensive public consultati­on.

UCT professor Anton Eberhard

said he was “dismayed by the lack of urgency and the proposed consultati­on process”.

“They’ve sat on the ministeria­l determinat­ion for a month. Now they’ve issued an unnecessar­ily complicate­d consultati­on document, and require comments only by May 7 2020. It will be months before power is actually procured.”

 ?? /Jeremy Glyn/Sunday Times ?? Successful power projects usually take up to a year to achieve financial close, which requires all contractin­g with Eskom to be done before financing can be secured.
Long process:
/Jeremy Glyn/Sunday Times Successful power projects usually take up to a year to achieve financial close, which requires all contractin­g with Eskom to be done before financing can be secured. Long process: