Cape Argus

BID TO GET CITY MILLIONS BACK

Council determined to recoup some of Cape Town Stadium costs

- Anél Lewis METRO WRITER

THE CITYof Cape Town is determined to recoup some of the billions it spent on building Cape Town Stadium. It is claiming on insurance for design changes that were made to the structure while it was being built.

It is lodging a civil claim against the constructi­on companies found by the Competitio­n Commission to have been involved in tender rigging and price fixing for the project.

It is in talks with the profession­al team to settle a disputed R200 mil- lion for constructi­on fees.

Although the initial constructi­on budget was estimated at R2.9 billion, costs ballooned to R4.5bn as the city raced to get the 2010 World Cup venue completed on time.

Deputy mayor Ian Neilson said in April that although the city had been suspicious about the rising costs, it had no option but to continue to meet Fifa’s deadline.

Pricewater­houseCoope­r forecast then that the stadium would run at an annual loss of R7.1m for the first three years. But the city revealed earlier this year that its operating costs amounted to more than R436m since the 2009/10 financial year. Its income for the period was just R92m.

The city has subsequent­ly spent R4m on advice from experts and lawyers to recover damages from the constructi­on companies that admitted to rigging the bids and fixing prices.

Two years ago, the Competitio­n Commission found that 15 constructi­on companies had been involved in tender collusion and price fixing for World Cup stadium tenders, including Wilson Bayly Holmes- Ovcon (WBHO), Stefanutti Stocks, Murray & Roberts and Group Five.

Cape Town Stadium, built in 32 months by Group Five and WBHO, was one of the affected stadiums. Although the 15 firms reached a settlement agreement and paid a combined R1.5bn in fines, the City of Cape Town is lodging a civil claim to recoup some of the money it was overcharge­d.

An advocate specialisi­ng in con- struction has advised the city that it can also claim profession­al indemnity insurance if there was evidence of negligence or misjudgeme­nt in the design of the stadium, said deputy city manager Mike Marsden.

He told the city’s financial oversight committee that design changes to the raking columns made the stadium less rigid, so an additional bracing had to be inserted.

Pressed for more detail, Marsden said the changes to the stadium design “made the stadium constructi­on more complex and costly”.

The city is also hoping to settle a disputed amount of R200m that was charged in profession­al fees. Marsden said that while the arbitrator­s found in favour of the profession­al team, which included architects, engineers and environmen­talists, the city’s contractua­l agreement allowed it to appeal against this ruling.

Marsden said the city’s legal team were meeting the profession­al team to resolve the matter, and was confident of “a reasonable and a fair settlement”.

The city has been saddled with the running costs of the stadium since December 2010 when the original operation company SAIL and Stade de France terminated a 30-year contract.

Although various events have been held at the stadium, the city needs to look at a long-term operating model if it hopes to break even.

A premium anchor tenant would ensure returns on the investment, and there has been speculatio­n that the Western Province Football Rugby Union might move from Newlands to Green Point. Other tenants mooted are Big Concerts, Ajax and Chippa United.

It is also hoped to change the zoning that restricts commercial activities on non- event days. Options here include a casino, a nightclub and possibly a hotel.

 ?? PICTURE: IAN LANDSBERG ?? PRICEY PLACE The city has had to pay the stadium running costs since December 2010
PICTURE: IAN LANDSBERG PRICEY PLACE The city has had to pay the stadium running costs since December 2010