Cape Times

Group Five’s interim losses are set to widen significan­tly

- Roy Cokayne

DELAYS with the completion by Group Five of the constructi­on of the $410 million (R5.29 billion) independen­t gas and oil-fired combined cycle power plant contract in Kpone in Ghana were expected to contribute to a significan­t widening in the year-onyear interim losses by the listed constructi­on and engineerin­g group.

Group Five said yesterday that it expected to report an almost 34 percent increase in the headline loss a share to 415 cents for the six months to December from the 310c a share loss in the correspond­ing period last year.

But shares in Group Five remained flat yesterday to close at R11.10 on the JSE.

Group Five added that trading within the constructi­on and engineerin­g, procuremen­t and constructi­on cluster was below the short-term guidance provided at the group’s year-end.

This, coupled with the impact of the additional costs expected to complete the Kpone contract, would impact the group’s 2018 half-year and full-year results and its available free cash reserves, it said.

Group Five said design delays, together with the late arrival of procured items on site following a change in Ghanaian law during the Kpone contract, were two key factors that had impacted the original contractua­l completion date of September 13 this year.

However, Group Five said the contract was also impacted by seawater tunnelling delays, which were resolved at the time of the release of the group’s annual results, although it was mentioned then that penalties could be incurred because these delays would result in a completion date after the contractua­l date.

But Group Five said the group had assessed its entitlemen­t together with claims on the Kpone contract and did not expect these penalties to further negatively impact on profit recognitio­n of the Kpone contract in the group’s 2018 financial year.

Group Five said the Kpone contract was now 97 percent complete with commission­ing, the only major remaining component, nearing completion, but further delays for a variety of reasons had been encountere­d since the annual results update.

It said the expected completion of constructi­on and commission­ing activities was now the end of February next year, which had resulted in a delay in milestone payments and an increase in the cost to complete the Kpone contract.

The Kpone contract was now expected to reflect an overall life-to-date loss, which would impact Group Five’s first-half 2018 financial year earnings and cash. “To fund the Kpone contract to its completion date, the group will be required to apply approximat­ely 50 percent of the €40 million (R608m) free cash held by its Investment­s & Concession­s business in Europe to the Kpone contract.

“Possible delay penalties due to the later completion date are quantified at $310 000 a day, up to a maximum cap of $62.5m.

“Against these possible delay penalties, the group is progressin­g its own entitlemen­t to contractua­l claims,” it said.

These include claims because of the late arrival on site of procured goods due to port delays following a change in Ghanaian law affecting the clearing of goods, a substantia­l claim against the design engineer sub-contractor and claims against certain sub-contractor­s due to poor design, delays and additional work having to be undertaken on the contract.

Group Five said these claims were progressin­g to finalisati­on with the various counter parties and “could be of substantia­l benefit to the group”, although the timing of the settlement­s was uncertain.

It added that pleasing progress had been made with the required legal and internal consultati­on process related to the decision to exit the constructi­on businesses where the group did not see the potential to establish sustainabl­e businesses, achieve targeted returns on capital and that were not core to its revised strategy.

 ?? PHOTO: SIMPHIWE MBOKAZI/AFRICAN NEWS AGENCY (ANA) ?? Group Five has reported delays in completing a R5.29-billion power plant in Kpone, Ghana.
PHOTO: SIMPHIWE MBOKAZI/AFRICAN NEWS AGENCY (ANA) Group Five has reported delays in completing a R5.29-billion power plant in Kpone, Ghana.
 ??  ??

Newspapers in English

Newspapers from South Africa