Cape Times

City Power takes on Eskom request

Coal cost increase is queried

- Siseko Njobeni

CITY POWER, Johannesbu­rg’s electricit­y utility, has punched holes in Eskom’s request to claw back billions of rands for coal costs, and questioned the increase in coal costs, while coal volumes for 2014/15 to 2016/17 fell.

Eskom has applied for recovery of R66 billion in respect for, among others, variances in revenue, coal, independen­t power producers (IPPs) and Open Cycle Gas Turbines (OCGTs) costs. The revenue variance accounts for 67 percent (R44bn) of the R66bn that Eskom wants to recover, while IPPs and coal account for R7.4bn and R3.5bn, respective­ly.

Speaking at the National Energy Regulator of South Africa (Nersa) hearings into the applicatio­n in Soweto, Frank Hinda of City Power on Friday shone the light on possible inefficien­cies that might have led to the high coal costs. Hinda said Nersa should apply the prudence and efficiency test on the coal costs. He said the regulator should reject the coal-related variances in the applicatio­n “in the interest of prudence, simply because Eskom burnt less coal. They should have spent less money instead of more.”

He also questioned the 36 percent increase in the price that Eskom paid for coal from cost-plus mines. “It is not clear why that was not anticipate­d at the time of the multi-year price determinat­ion (MYPD) applicatio­n, because the costplus and long-term contracts are supposed to have stable prices,” said Hinda.

He said Eskom was increasing­ly relying on the expensive short-term contracts. “We know that, for the foreseeabl­e future, we will be burning about 110 million tons of coal. That is guaranteed. Why do we have short-term contracts? Those are the things that we ask Nersa to do further assessment of,” he said. Hinda said at least R19bn should be taken out of the applicatio­n, which would bring Eskom’s claim to R47bn.

In its applicatio­n, Eskom attributed the high coal costs to underperfo­rmance of cost-plus mines. The utility attributed the reduced volumes to lack of funding and investment in costplus mines. As a result, Eskom had to either truck or rail coal from other power stations, resulting in the higher costs.

Eskom general manager for primary energy Dan Mashego on Friday told the Nersa hearings that the new coal contracts that Eskom entered into came at a high price. “The historical cost of sourcing coal has benefited Eskom. That is changing, because new coal contracts come at a higher price,” said Mashego.

Eskom’ acting chief financial officer Caleb Cassim on Friday defended the R66bn that the company wanted to claw back from electricit­y users. “Variances can be linked to two key sources, which are increases in costs due to a changing environmen­t and assumption­s made for purposes of the MYPD 3 revenue decision, which did not materialis­e. The Regulatory Clearing Account (RCA) methodolog­y allows for certain elements of Eskom’s revenue and costs to be in favour of Eskom, where our costs were higher than anticipate­d and in favour of the consumer in instances where we spent less than planned,” said Cassim.

Eskom group executive for generation Thava Govender on the other hand explained the rationale for the increased usage of the expensive OCGTs. Govender said the decision to initially exclude Eskom from building new electricit­y capacity was the genesis for the constraine­d power system. The subsequent requiremen­t for Eskom to keep the lights on at all costs led to the increased usage of the diesel-guzzling generators.

“As the de facto supplier of last resort, our mandate required us to use whatever resources we had in order to keep the lights on. The electricit­y system was constraine­d and a decision was taken to delay maintenanc­e, which then led to deteriorat­ion of plant, most of which was already in midlife. This is unfortunat­ely the time when you need to do more intrusive maintenanc­e, but we had to balance demand and supply and didn’t have the opportunit­y to do maintenanc­e.

“We did manage in subsequent years to remove the requiremen­t to keep the lights on at all costs from our shareholde­r compact and resumed with proactive maintenanc­e. However, it must be noted that even in retrospect we believe that there is little we could have done differentl­y as a supplier of last resort given the conditions we faced in those years. In this regard, Eskom has agreed to implement the approach to sacrifice the additional OCGT costs and recovering at coal cost equivalent. The costs we have applied for in this RCA were prudently incurred in the implementa­tion of our mandate to supply reliable electricit­y,” he said.

 ?? PHOTO: BHEKIKHAYA MABASO / AFRICA NEWS AGENCY / (ANA) ?? Community members are protesting at the Eskom third multi-year price determinat­ion at Walter Sisulu Square Soweto in this file picture. Eskom has requested Nersa to be allowed to claw back costs.