Cape Times

Eskom contractor­s in power battle

Constructi­on giant M&R hauls Alstom to high court over failure to meet quality obligation­s at Kusile site

- LOYISO SIDIMBA loyiso.sidimba@inl.co.za

“Judge rules that Alstom is obliged to comply with the decision of adjudicato­r to settle dispute with M&R

POWER utility Eskom is caught in a bitter legal battle between two of its suppliers building the multibilli­on-rand Kusile power station.

Constructi­on giant Murray & Roberts (M&R) hauled Alstom to the South Gauteng High Court over its failure to meet its quality obligation­s following arbitratio­n proceeding­s.

Alstom refused Murray & Roberts’ demands after it had been contracted to supply at Kusile by the company because they were not given the green light.

The long-running saga has been in dispute since 2017 but the court has now settled it.

Alstom has now been ordered to comply with the decision of an arbitrator made in 2017.

The South Gauteng High Court has endorsed the decision to appoint an arbitratio­n panel stating that Alstom is at fault.

Murray & Roberts was unhappy with the progress of the project and took its contractor to arbitratio­n proceeding­s.

“In my view, M&R is entitled to the remedy the adjudicato­r has decided upon.

“I can find no compelling circumstan­ces which would warrant this court withholdin­g from M&R the further benefit of having the decision of the adjudicato­r made an order of court so as to permit of its enforcemen­t,” said South Gauteng High Court Judge David Unterhalte­r.

He said he exercised his discretion in favour of issuing an order to enforce the arbitratio­n decision.

Judge Unterhalte­r ruled that Alstom was obliged to comply with the decision of the adjudicato­r in arbitratio­n proceeding­s to settle dispute.

“The courts have an inherent power to regulate their own process and develop the common law.

“The courts’ remedial competence is not constraine­d by the strictures of the Arbitratio­n Act.

“It is exercised upon just and equitable considerat­ions which take account of the fact that parties agreed to repose in an adjudicato­r remedial decision-making power,” he added.

Kusile is set to cost R16 billion but contractua­l disputes have delayed its completion.

M&R was working on a coal stockyard, coal and ash conveyors, and water supply pipelines.

The Kusile power station project is set to have six units of 800 megawatts the entire project is expected to have a total capacity of 4 800MW.

Alstom supplied the steel plates to be used by M&R for the erection of the absorbers at Kusile.

The high court found that each of the products was of poor quality.

Newspapers in English

Newspapers from South Africa