Daily Dispatch

Prasa lags way behind on massive new trains’ project

Officials put up brave face as agency fails to meet its own deadlines

- By ANDISWA MAQUTU

THE Passenger Rail Agency of SA (Prasa) is severely behind schedule on upgrades necessary for its new trains procured in a R51-billion contract.

Internal documents show Prasa’s own deadlines for the constructi­on and improvemen­t of perways‚ platforms and other structures have been missed.

This is in addition to the agency not having depots ready to test the trains.

On Wednesday‚ Prasa confirmed a Business Day report on the depot delays but said the other upgrades were not necessary for the testing of the trains.

Spokesman Sipho Sithole maintained it was on track with its priority corridor‚ which runs from Park Station in Johannesbu­rg to Pretoria‚ and its depot modernisat­ion programme.

However‚ a Prasa report tabled before former chief executive Lucky Montana in May‚ stated the agency was concerned “reputable contractor­s” would not commit to the “tight constructi­on deadline”.

The depots need to be ready by November and the perways by next year‚ though those improvemen­t are likely to be complicate­d as they will be on facilities already in use.

The agency also said Braamfonte­in had been earmarked as the priority depot for the testing of the new trains but it was changed to Wolmerton in Pretoria.

Sithole said on Wednesday there was “no work to be tendered for” at Wolmerton‚ which is puzzling as the Braamfonte­in depot would have needed work costing billions but the tender deadline was missed.

The documents show a tender deadline for Wolmerton was changed from August to November last year.

The “re-advertised” Wolmerton perway and facilities tenders were still under evaluation‚ the report said‚ even though the perway for the testing section needs to be completed by the beginning of next month.

A test track – that costs more than R200-million – needs to be completed by November to ensure trains can reach the required speed.

“The trains will be tested at our Wolmerton depot using the track test facility that has been earmarked‚” said Sithole.

The document shows a range of improvemen­ts are unlikely to be completed on time: designs for new drainage in Centurion are only 60% complete despite a December deadline; tenders for drainage improvemen­ts in Doornfonte­in and Jeppe stations are still being evaluated even though work should have started last year; and tenders to have platforms rectified at Park and Pretoria stations have not been approved despite a start date of last year.

A request for proposals for platform rectificat­ions on the Johannesbu­rg-Pretoria route has not been completed even though the deadline for the work was April this year.

When asked about the delays‚ Sithole said this was “part of Prasa’s governance processes”.

The 600 new trains have been procured through the Gibela Rail Transport Consortium.

The depot modernisat­ion is expected to cost R5-billion.

This is not related to a locomotive­s contract that was inflated to R4.8-billion and that has been criticised for its locomotive­s being too high for the existing infrastruc­ture. — BDlive

 ??  ?? DILEMMA: The Passenger Rail Agency of SA is severely behind schedule on upgrades necessary for its new trains procured in a R51-billion contract, internal documents show
DILEMMA: The Passenger Rail Agency of SA is severely behind schedule on upgrades necessary for its new trains procured in a R51-billion contract, internal documents show
 ??  ?? OUT: Former chief executive Lucky Montana
OUT: Former chief executive Lucky Montana

Newspapers in English

Newspapers from South Africa