Daily Dispatch

PROJECTS EXPIRED: R250m ‘WASTED’

Abattoirs, dairy farms, roads and heritage site stalled for years

- BONGANI FUZILE

At least a quarter of a billion rand ploughed into projects meant to benefit communitie­s in the Eastern Cape has been wasted in the past five years.

A Dispatch team travelled across the province counting projects lying unfinished and abandoned.

These include abattoirs, dairy farms, roads and a heritage site.

Work began in 2016 on a R70m project in Butterwort­h, Mnqumashe Abattoir, that was supposed to be finished by September 2017.

However, the high-throughput cattle and sheep abattoir remains incomplete because the department of rural developmen­t & land reform failed to pay R800,000 it owed to a constructi­on company. This was after the department had already spent R35.15m on the project. The outstandin­g balance is R24.84m.

This project was started when the department received an applicatio­n from livestock farmers in Butterwort­h seeking financial assistance to recapitali­se the dilapidate­d old Butterwort­h tannery into an abattoir.

In an internal progress report, the department says the constructi­on was 60% completed.

A document signed by the department's infrastruc­ture director Ncumisa Ntshona and provincial head Zolile Pityi states: “Performanc­e guarantee by the contractor has expired ... currently the work has stopped on-site due to non-payment of the contractor’s invoice of March 2019 of R797,000.”

A consulting company for the project was appointed in 2014 at R3.16m. Fees have since been adjusted to R10.4m.

Another gaping hole is a mooted bridge and 10km access road at Gqunu village in Mhlontlo municipali­ty. The value of this project is R72.6m. Five years down the line, the project is still unfinished.

Another incomplete project is constructi­on of the R54.1m Zuurberg Heritage site in Addo.

Constructi­on phase two of the Ncera Macadamia Irrigation system, to the value of R49m, has been approved but is yet to be implemente­d. The land lies cleared and ready for planting, with contour furrows ploughed. The Dispatch could find no record of money spent by the department on the project, though it was approved in 2015 and was meant to have started in the same year.

However, Joe Jongolo of Ncera Macadamia was upbeat. “The department is still very much committed to providing the bulk water supply, and they are in the process of appointing a contractor in the new year.”

A senior department official said the problem was “incompeten­t leadership”“It is all in the leadership. The more the project delays, the more money we pay ... We previously had TamTam Gobozi running these projects. She left without finishing any. Now we have Ncumisa Ntshona, who confirmed in a progress document that the department has failed to pay R797,000 to a contractor

— something that has stalled this R70m abattoir project. Really, how’s this possible to stall a project for so little money?” said the source.

The department failed to respond to questions sent last week. Two other collapsed projects were found in Cala and in Dordrecht, part of the Chris Hani District Municipali­ty (CHDM) which were started more than five years ago.

In Cala an abattoir worth R5.5m has been vandalised. In Dordrecht, a R6.3m cheese factory has “collapsed”.

When the Dispatch team visited the Cala abattoir in September, all the copper pipes, windows, doors and expensive abattoir machinery had been removed. No-one was guarding what was left of the structure.

CHDM spokespers­on Thobeka Mqamelo said the intention was to enable local farmers to access the market as part of the CHDM Livestock Improvemen­t Programme. “The district entered into a private partnershi­p agreement with a local farmer as the municipali­ty could not run such an establishm­ent on its own. The agreement, unfortunat­ely, fell off after the partner passed away,” she said. “The project in question was budgeted at R5.5m and a security company is on-site.”

On the Dordrecht cheese factory, Mqamelo said the project collapsed after relations among the communal and commercial farmers who ran the project became strained beyond the point of possible reconcilia­tion. The situation was worsened by the severe drought as milk production dwindled, she added.

“However, plans are afoot to ensure the project is operationa­l as there is a lease agreement entered into between the local municipali­ty and a local dairy,” said Mqamelo.

Newspapers in English

Newspapers from South Africa