Breach of agreement could cost Ingquza Hill R126m

Cogta could not resolve Lusikisiki mall contract tangle

- BONGANI FUZILE

A prominent businessma­n is demanding millions of rand from one of the poorest Eastern Cape rural municipali­ties after a failed shopping mall deal.

Dumisa Dlatu’s Quanza Group consortium is taking legal action against the Ingquza Hill local municipali­ty which it says must pay out R126m after a 40-year lease agreement was not honoured by the council.

Dlatu and the municipali­ty signed an agreement in 2005 that Quanza Group would construct a multimilli­on-rand mall in Lusikisiki but the municipali­ty, which encompasse­s the towns of Flagstaff and Lusikisiki, reneged on the deal.

Dlatu’s lawyers, SC Vutula & Co, sent a letter of demand to the municipali­ty 15 months ago asserting that before the municipali­ty did a U-turn on the deal, Quanza Group had already secured tenants for the mall, as well as spending millions clearing the site and building a few structures there. Quanza’s claim includes: R39,396,424 for constructi­on of the 4,215 m² structures on the site; R65,381,052 for loss of income since 2013; and gross annual income of R22,000,000 for the remaining years of the 40year lease.

“Therefore, the municipali­ty is liable to pay the claimant damages in the amount of R126,777,477,” states the letter which was signed off by lawyer Solomzi Vutula.

Before the municipali­ty went cold on the project, it entered into a 30-year lease agreement with the Quanza Group and this was subsequent­ly extended to 40 years.

The Dispatch has seen a letter dated December 12 2011 from the municipali­ty’s former municipal manager, Mluleki Fihlani, asking Quanza to “speed up” the developmen­t.

“The council hereby indemnifie­s the developer, Quanza or any cessionary that the correct zoning will be effected by the council,” the letter states.

“The developer is permitted to commence constructi­on work ... council warrants that all municipal services including water, sewer and stormwater will be facilitate­d for the constructi­on and therefore it is our priority to have sufficient capacity to accommodat­e the design requiremen­ts of the shopping centre as advised by the consultant­s.”

Vutula said the municipali­ty had been required to provide the consortium with the title deed and surveyor general diagrams and to apply for rezoning of the constructi­on site.

It was also required to upgrade infrastruc­ture, including water and sanitation, storm water drainage and electricit­y, to accommodat­e the proposed shopping centre.

Vutula said as a result of the breach of the agreement, his client had not been able to complete constructi­on of the mall causing serious financial losses.

Dlatu declined to comment, saying the matter was sub judice.

Municipal spokespers­on Zamuxolo Matwasa said they were engaging with the com

The matter is before the court but we can safely say it revolves around the breach of agreement

pany’s lawyers.

“The matter is before the court but we can safely say it revolves around the breach of agreement.

“We [have been] engaging the company since December 2019 through the lawyers regarding the applicatio­n brought by the municipali­ty to cancel the lease agreement,” Matwasa said.

The matter is to be heard by the high court in Mthatha but at the time of writing, the Dispatch was not provided with a date for this.

Dlatu had earlier raised the matter with Cogta MEC Xolile Nqatha.

Nqatha’s spokespers­on, Makhaya Komisa, said: “The MEC is aware of the matter as he was approached by Mr Dlatu to facilitate a resolution.

“In hearing his side he had thought the matter was easy but, upon hearing the side of the municipali­ty, it became clear the matter requires a determinat­ion by a court of law, as the municipali­ty also believes it has a strong case.”