Diamond Fields Advertiser

Work still not finished on Legislatur­e

- SANDI KWON HOO CHIEF REPORTER

AN AMOUNT of R14,5 million has been paid in rent for the lease of the BP Jones and Metlife Towers buildings for the duration of the refurbishm­ent of the Northern Cape Provincial Legislatur­e precinct. The precint is still incomplete due to substandar­d work.

The acting executive manager of committees, research and informatio­n services, public education and communicat­ions, Nathalia Borchard, indicated that the Legislatur­e had paid R631 000 per month for these two buildings over a period of 23 months. “The amount excludes the lease of official parking space.”

She explained that not all repair and renovation work had been completed to “absolute satisfacti­on”.

“Technical reports indicating our concerns have been submitted to the contractor in this regard. It is the responsibi­lity of the appointed profession­al team to ensure that all identified work of substandar­d quality is attended to by the contractor and their subcontrac­tors before a practical handover will be done.”

She stated that the contractor was requested to cordon off all unsafe areas during constructi­on.

“All internal key stakeholde­rs have been requested not to enter unsafe areas. Members and staff of the legislatur­e were also informed that work will still be continuing on site as constructi­on has not been completed. They were requested to exercise caution and patience as most of the work must be completed to our satisfacti­on.”

She said the legislatur­e vacated the Metlife Towers building on November 30 and the BP Jones building on December 12, as agreed upon with the respective management.

“All office furniture of the legislatur­e’s political offices and the administra­tion was delivered to the precinct by December 14 2018, the date of its annual closure.”

Borchard said penalties had been deducted from the contractor because of the delays in completing the project.

She added that four extensions were granted to the contractor totalling 132 days. “A total of 228 days were applied for by the contractor, but only 132 days were granted.”

She stated that although work came to a practical standstill for several months, the contractor was never physically off-site. “Even during the period of operationa­l standstill, they maintained some presence on site. The contractor did not stay on schedule and work practicall­y came to a standstill for approximat­ely five months.”

Borchard indicated that the contractor was paid an amount of about R22,4 million for work done so far.

“The work has been certified by the profession­al team. The remainder of the total project cost is reserved for the outstandin­g work as per the scope and snagging phase. The legislatur­e is also holding 10 percent of the aforementi­oned amount as a retention fee.”

She stated that the problem of the undergroun­d water in the basement would remain a “matter of proper long-term maintenanc­e”.

“The legislatur­e was built on a fluctuatin­g water table. After the conclusion of this project, the legislatur­e will have to continue maintainin­g the water pumps and storm water system, joining efforts with local government, as the latter plays a critical role in the external stormwater infrastruc­ture.”

She said that most of the structural, electrical damages and cracks had been repaired, especially around the buildings that were recently occupied at the facility as part of the sectional handover.

“Other outstandin­g items form part of the final phases of the project, while identified substandar­d items will be attended to during the ongoing snagging phase. Although the members’ wing has also been occupied, most of the bathrooms, the curtain wall and some of the walls with effloresce­nce must still be completed.

“There is also still a lot of work outstandin­g in the Patlelo (main entrance), Speakers wing and at the chamber area.”

Borchard added that it was not necessary for the Department of Labour to issue a certificat­e of occupation before occupation could take place.

“The Department of Labour does not issue any certificat­ion except for conducting occupation­al health and safety inspection­s. A certificat­e of occupancy is evidence that a building complies substantia­lly with the plans and specificat­ions that have been submitted and/or approved by the municipali­ty. Therefore no certificat­e will be issued by the department of labour.”

She indicated that the contractor, as the responsibl­e agent, was requested to ensure that any relevant certificat­es be obtained and submitted to the Legislatur­e without delay.

“It must, however, be noted that no structural changes have taken place in that no walls have been demolished or new walls build. The Legislatur­e building plan is still the same, however, we deem it important that we be furnished with electrical and other important certificat­ion where necessary.”

Borchard explained that not all toilets at the occupied buildings were working properly.

“Some were still under renovation at the time of the annual closure. The contractor was requested and has committed to ensure that all are attended to with speed. The Legislatur­e management has alerted the principal agents to ensure that this commitment will be honoured as it affects the basic occupation­al health and safety of employees and Members of the Provincial Legislatur­e.”

She stated that the lifts would only be commission­ed after all the required work around it has been completed.

 ??  ?? Millions in rent has been spent on the rental of the BP Jones Building. Picture: Soraya Crowie
Millions in rent has been spent on the rental of the BP Jones Building. Picture: Soraya Crowie

Newspapers in English

Newspapers from South Africa