Diamond Fields Advertiser

WATER CUTS ‘INEVITABLE’ – SOL

- SANDI KWON HOO SANDI.KWONHOO@ACM.CO.ZA

WHILE the city’s water situation remains in a precarious state and repairs are under way, Sol Plaatje Municipali­ty has advised that water interrupti­ons are “inevitable”.

Bigen Africa project engineer Rikus Rossouw estimated that emergency repair work would improve the water supply within the next 18 months.

“Once emergency repairs are completed, the daily and nightly water interrupti­ons will come to an end,” said Rossouw.

He explained that a gasket in Midlands, which could burst at any moment, needed to be urgently replaced.

“It will take at least three days to replace it during a planned shutdown. If it bursts before then, it will result in an emergency shutdown where the whole town will be without water for a couple of days.”

Rossouw said that three contractor­s were working at the Riverton purificati­on plant.

“Isiphethu Peaches joint venture has been repairing burst pipes without having to shut down the town’s water supply since February 19. However, some leaks are so large that they can only be fixed during a water shutdown. A total of 25 leaks have been identified along the main pipeline between Riverton and Kimberley.”

He attributed the low water levels at the reservoir to a lack of maintenanc­e and mechanical and technical challenges.

“Without the necessary capacity, not enough water is reaching Kimberley. We are pumping about 120 mega litres from the river for purificati­on while 80 mega litres is fed into the reservoir where daily consumptio­n equals to about 80 mega litres.”

Rossouw indicated that only two of the four clarifiers were in operation at the old plant, while only six out of the 12 filters and three out of six pumps were working.

“We are waiting for isolation valves to fix leaks on the old plants and require another transforme­r to enable all four high-lift pumps to work so that water can

be pumped to Newton Reservoir. The current transforme­r does not have the capacity to power up all the high-lift pumps.”

He added that they were in the process of upgrading the old purificati­on plant over a 10-month period, so that they can start work on the new water purificati­on plant.

“The new plant is over 40 years old and requires mechanical and technical attention. It also needs to be automated as everything is still being operated manually.”

Rossouw stated that while the water appeared to be off-colour, it was within the acceptable norms for human consumptio­n.

“The water is tested on a regular basis and any bacteria can be eliminated by boiling the water. Sediment enters the pipeline during regular shutdowns as well as the filters that are not running at full capacity,” he explained.

Sol Plaatje municipal manager Thapelo Matlala said that 35 projects were being undertaken through the R2.5 billion grant to address critical maintenanc­e on

bulk water supply infrastruc­ture over the next seven years.

“Work has commenced on three contracts with a total constructi­on value of R88.2 million. R18 million is being spent on emergency leak repairs, a R40 million contract was awarded for the new water treatment plant chlorine

chemical dosing system and R28 million has been allocated on an emergency flow and quality monitoring system,” said Matlala.

He added that a further two projects would be awarded by March 15, while three other tenders would be advertised for maintenanc­e interventi­ons to improve water supply production and reduce supply interrupti­ons.

“While these constructi­on works are being carried out, residents are reminded that the interrupti­on of supply is inevitable. These interrupti­ons will vary in duration and frequency and will be communicat­ed formally to all consumers. As the interrupti­ons will be well-planned, the duration and frequency will be minimised at all costs.”

Matlala stated that they were in the process of putting two dysfunctio­nal clarifiers back into operation at the old treatment plant.

“Commission­ing of this clarifier will be completed on March 8. The second clarifier is being cleaned and the valves have been repaired. Both these will improve water production by 15 mega litres per day.

“Filter media has been replaced on two filter bays at the new treatment plant to improve the filtration process and overall water production capacity.”

He added that the Bigen Africa team and Ekapa Mining, which had committed funding of R10 million towards efforts to address the water challenges, were providing support to the municipali­ty.

“We do not take residents’ patience for granted. Our efforts are purely aimed at improving water service delivery and ultimately attaining an uninterrup­ted and quality supply,” Matlala concluded.

 ?? ?? Rikus Rossouw, Bigen project engineer, with Lucky Moyahi, Bulk Facility for Infrastruc­ture Programme co-ordinator at Sol Plaatje Municipali­ty, during a media tour at the old water plant at Riverton.
Rikus Rossouw, Bigen project engineer, with Lucky Moyahi, Bulk Facility for Infrastruc­ture Programme co-ordinator at Sol Plaatje Municipali­ty, during a media tour at the old water plant at Riverton.
 ?? Pictures: Soraya Crowie ?? A clarifier being cleaned. Each clarifier can hold 10 megalitres of water.
Pictures: Soraya Crowie A clarifier being cleaned. Each clarifier can hold 10 megalitres of water.
 ?? ?? Only two of the four clarifiers are operationa­l.
Only two of the four clarifiers are operationa­l.

Newspapers in English

Newspapers from South Africa