Engineering News and Mining Weekly

Cape Town bulk sewer upgrades making headway

- SABRINA JARDIM | CREAMER MEDIA WRITER

The City of Cape Town started work on the Milnerton and Cape Flats bulk sewer upgrades earlier this year and is on track to complete both by 2025, says City of Cape Town Water and Sanitation MMC Councillor Zahid Badroodien.

The Milnerton project entails the constructi­on of a new bulk sewer in Montague Gardens using innovative micro-tunnelling technology. The City will also extend and connect the Edgemead and Century City bulk sewers into the new infrastruc­ture.

The upgrade includes the installati­on of a sandtrap and screening facility at the Koeberg Road pumpstatio­n. This is set to improve performanc­e and reduce breakdowns caused by foreign objects entering the pumpstatio­n.

The City completed a condition assessment for the project in 2019 that confirmed the need to start planning the upgrade of the bulk sewer.

“The current Milnerton Bulk Project comes as a result of planning, as well as the fast deteriorat­ion of the existing system, which further confirms that it was the correct starting point,” explains Badroodien.

Meanwhile, planning for the Cape Flats Project began in 2015, with the first phase involving the constructi­on of the Cape Flats 3 bulk sewer.

On completion, the next phase will comprise the current Cape Flats 1 and 2 bulk sewer upgrades, which will accommodat­e some of the flow, thereby making it possible to access the system safely. “Both systems will ensure that new developmen­ts in their catchment can proceed and benefit from the growth of the city and associated economy,” Badroodien assures.

Pipe replacemen­t is part of the City’s strategy to decrease sewer spills over time, which includes major bulk sewer upgrades, the proactive cleaning of sewer lines, the resourcing of sewer spill response teams and digital telemetry systems for early warnings on sewer spills.

Based on preliminar­y data, these interventi­ons have led to a 30% downward trend in reported spills in Cape Town over the past two years.

Over the next three years, the city will invest R1.4-billion in major bulk sewer upgrades to the Cape Flats, Philippi, Milnerton and Gordon’s Bay lines, in the Western Cape.

Hence, Cape Town is ramping up infrastruc­ture investment, with a 223% increase in its water and sanitation infrastruc­ture budget – from R2.3-billion in 2022/23 to R7.8-billion in 2025/26.

New Technology

Spirally wound pipeline technology has been employed for the Cape Flats Project. This trenchless technology is applied through the existing manholes, whereby a continuous liner is formed inside the manhole as it is introduced into the pipe.

This technology has ensured minimal disruption to residents and roads, and is also cost-saving, compared with open-trench convention­al constructi­on.

The Milnerton bulk sewer will be constructe­d using tunnelling equipment, except where open trench or geotechnic­al conditions are specified or restrict the use of equipment.

Badroodien notes that tunnelling has limited impact on the surface level; therefore, daily activities are not affected.

Moreover, the installed pipe has a highdensit­y polyuretha­ne lining, which is inert to sewer gas corrosion and provides for a more than 100-year serviceabl­e life.

During the upgrades, the City of Cape Town faced several challenges, including extortion on both sites, which resulted in delays and damage to contractor­s' equipment.

Material imports for the Cape Flats bulk sewer upgrades were delayed, owing to the Russia-Ukraine war and harbour limitation­s in South Africa, while hard-rock excavation­s in Milnerton delayed the anticipate­d progress.

Despite challenges, the first three work packages were completed at the end of last month, with Badroodien describing this as “the first milestone for the current financial year”.

The remaining work packages are being prepared, with start dates expected in February 2024.

Considerin­g the works are still in the first year and that delays have been properly handled, the contractor has achieved the programmed works up to the percentage progress required.

“The City is working hard to give effect to its Water Strategy to ensure sufficient and highqualit­y drinking water into the future, as well as a reliable wastewater service, thereby ensuring a dignified service to citizens and a healthy environmen­t,” Badroodien concludes.

 ?? ?? BEST TO INVEST Over the next three years, the City of Cape Town will invest R1.4-billion in major bulk sewer upgrades to the Cape Flats, Philippi, Milnerton and Gordon’s Bay lines
BEST TO INVEST Over the next three years, the City of Cape Town will invest R1.4-billion in major bulk sewer upgrades to the Cape Flats, Philippi, Milnerton and Gordon’s Bay lines
 ?? ?? THE FUTURE IS NOW
Pipe replacemen­t is part of the city’s strategy to futureproo­f bulk sewers
THE FUTURE IS NOW Pipe replacemen­t is part of the city’s strategy to futureproo­f bulk sewers

Newspapers in English

Newspapers from South Africa