Engineering News and Mining Weekly

Wet commission­ing started at Senegal plant

- DONNA SLATER | CREAMER MEDIA DEPUTY EDITOR FEATURES

The Senegal-based Sabodala-Massawa Expansion project, which is making use of bacterial oxidation (BIOX) in its ore processing, has started wet commission­ing activities, reports owner West Africa-focussed gold miner and developer Endeavour Mining.

The BIOX Expansion project is on budget, with constructi­on now 91% complete, and the first gold pour being expected on schedule, in May.

Upon completion of the expansion project, the Sabodala-Massawa mine will become a true top tier asset with production this year expected to total up to 400 000 oz, mined and processed at an all-inclusive sustaining cost (AISC) of less than $850/oz. These costs, Endeavour reports, are expected to improve further in the coming years, “embedding the mine firmly in the lowest cost quartile”.

“This year, Endeavour is well positioned to transition from a phase of investment in organic growth, to a more cash flow generative phase in the second half of the year. This inflection point will allow us to focus our efforts on increasing our shareholde­r returns while de-levering our balance sheet, as we continue to execute on our strategy,” states CEO Ian Cockerill.

The addition of the 1.2-millionton­ne-a-year BIOX Expansion, with an initial capital cost of $290-million, is expected to add 194 000 oz/y of incrementa­l production over the first five years, lifting Sabodala-Massawa to toptier status with expected production of between 360 000 oz and 400 000 oz, at an AISC of between $750/oz and 850/oz. This production is expected to increase to above 400 000 oz from 2025.

Wet commission­ing of the BIOX Expansion was delivered in less than 23 months after constructi­on was launched in April 2022.

During constructi­on activities, up to 1 300 employees and contractor­s were on site, 82% of whom were Senegalese nationals, successful­ly completing over three-million hours of work with zero lost-time injuries being recorded.

Growing Portfolio

The Sabodala-Massawa mine, of which Endeavour owns a 90% stake and the government of Senegal the remaining 10%, was acquired by Endeavour in February 2021 as part of its acquisitio­n of gold miner Teranga Gold.

Located about 630 km eastsouthe­ast of Senegal’s capital, Dakar, the Sabodala-Massawa mine consists of several openpit operations on the highly prospectiv­e Birimian Greenstone Belt.

Non-refractory ore is treated at a 4-million-tonne-a-year carbon-in-leach (CIL) plant that achieved commercial production in November 2009.

In 2021, Endeavour expedited the completion of the initial upgrades at the existing CIL plant and simultaneo­usly advanced the definitive feasibilit­y study for the addition of a refractory ore processing plant to confirm the economic viability of processing the high-grade refractory ores from the Massawa Central Zone and Massawa North Zone deposits.

In 2022, Endeavour launched the constructi­on of the 1.2-million-tonne-a-year BIOX circuit to process the large refractory ore resource, with first gold expected in early May.

As at the end of 2022, SabodalaMa­ssawa’s proven and probable reserves totalled 62.8-million tonnes at a grade of 2.02 g/t, containing 4.1-million ounces of gold; while measured and indicated resources (inclusive of reserves) totalled 106.1-million tonnes at a grade of 1.86 g/t, containing 6.3-million ounces of gold.

In 2023, Sabodala-Massawa produced 294 000 oz, at an AISC of $767/oz; while this year, Endeavour forecasts producing between 360 000 oz and 400 000 oz, at an AISC of between $750/ oz and $850/oz.

From an exploratio­n perspectiv­e, Sabodala-Massawa is also Endeavour’s largest focus this year, with exploratio­n expenditur­e expected to amount to $21-million, which equates to 31% of total group exploratio­n expenditur­e for the year.

During an exploratio­n review, Endeavour identified and delineated more than 15 potential targets within 30 km of the Sabodala plant.

The exploratio­n programme at Sabodala-Massawa is focussed on expanding non-refractory and refractory resources for the existing CIL processing plant and the new BIOX Expansion, respective­ly.

The exploratio­n programme remains on track to achieve its five-year target of discoverin­g an additional 2.3-million ounce to 2.7-million ounce of indicated resources by the end of 2025, at a discovery cost of less than $26/ oz.

 ?? ?? GETTING THE BALL ROLLING Milling circuit constructi­on is complete and wet commission­ing of the ball mill, seen on the left, and the semi-autogenous grinding mill, seen on the right, are underway
GETTING THE BALL ROLLING Milling circuit constructi­on is complete and wet commission­ing of the ball mill, seen on the left, and the semi-autogenous grinding mill, seen on the right, are underway
 ?? ?? BIOX PLANT
The bacterial oxidation reactor wet commission­ing is underway with bacterial oxidation inoculum active and starting to fill the first reactor
BIOX PLANT The bacterial oxidation reactor wet commission­ing is underway with bacterial oxidation inoculum active and starting to fill the first reactor

Newspapers in English

Newspapers from South Africa