George Herald

Public wants to know all regarding Caledon St contract

-

This letter from J van der Westhuizen includes comments from the George Municipali­ty:

As residents in Caledon Street we have been inconvenie­nced for some time now. I feel it is important that the following be made public knowledge and that these claims should, at the very least, be investigat­ed. The lack of urgency throughout the entire project, the chaotic arrangemen­ts, often on short or no notice, and the misleading communicat­ion regarding time frames have left many of us questionin­g whether the municipali­ty is in fact being honest with us.

I was already alarmed when the contractor milled out the entire road surface and simply tipped material in the side entrances as their answer to traffic control! Surely if this was done in sections it could have been less disruptive for residents. The contractor did this without consulting with the residents and without proper communicat­ion with commuters. They were left scurrying aimlessly through the side streets looking for a way through the madness.

The contractor is now disputing the results of the road surface tests and this is causing yet more delays. If the entire lane is to be taken out and replaced, the inconvenie­nce will persist. Another, more sinister option would be for the municipali­ty to brush over the deficienci­es and simply hide it from the public. Would the municipali­ty withhold such informatio­n?

The article in the George Herald of 14 February, "Faulty asphalt delays Caledon road works", refers.

The municipal communicat­ions chief raises some interestin­g points.

Q: According to her the contractor­s must source the asphalt from an approved asphalt supplier.

A: The George municipal PPPFA conditions required that the contractor make use of local suppliers. With reference to Caledon Street, the contractor contracted a supplier that made use of a temporary batching plant located closed to the airport, which is deemed to be within the George municipal area, and thus local.

Q: I have been told that the asphalt for the lane in question was not sourced from an approved asphalt supplier. An approved asphalt supplier needs to have an air emission licence with stringent regulation­s in place. Apparently the plant supplying this asphalt did not have and still does not have authorisat­ion to supply to this contract.

A: Yes, the municipali­ty was made aware, but as the municipali­ty does not have a contract with the supplier, but only with the contractor, the municipali­ty can only comment on the material supply by the contractor, and as stated in the article, the municipali­ty rejected portions of the BTB layer supplied. The plant, air emission licence and other regulation­s applicable to asphalt manufactur­ing are applicable to the asphalt supplier, and not the contractor.

Q: I was also told that the municipali­ty was made aware of this. So why do we know nothing?

A: The municipali­ty, after being made aware of this, did two things. One: request clarificat­ion surroundin­g the relationsh­ip between the contractor and the supplier, and two, order additional independen­t tests on roads, where the same batching plant's material was used, to ensure that the quality of asphalt complied with the approved mix design. The outcomes of that test confirmed that the BTB and asphalt supplied conformed to the approved design.

Q: On a similar contract in the same municipal area, done at roughly the same time, the contractor handed in what seems to be a blatantly falsified and copied mix design. This was brought to the municipali­ty's attention and is currently an ongoing investigat­ion of fraud by the SAPS. Why is this not public knowledge?

A: The contractor is required to submit a mix design for approval from his supplier.

The mix design was submitted and accordingl­y approved. Again, take note that the municipali­ty deals, in terms of the signed contract, with the contractor and not his suppliers. The case of fraud is being investigat­ed by SAPD against the supplier and not the contractor.

Q: At least the communicat­ions chief admits that the mix design forms the basis of such pre-approved design. It is hoped the mix design for this road was scrutinise­d and the underlying tests supplied.

A: As mentioned above, the consultant approved the mix design after comparing the proposed design content against the design. Q: Given the brittle state of the economy, can the citizens of George honestly afford for millions of rand being lost to business outside of its boundaries? The contractor was brought in by the DA-controlled municipali­ty after tenders were put out.

One can only guess that the municipali­ty chose an outside contractor for the tender as it was felt that maybe someone else needed a chance to do the work in George. The results have been disastrous while the DA has persisted to overlook the proven, reputable companies locally and also its own taxpayers.

By this logic, wouldn't it be fair to say maybe someone else needs the chance to run our city? With the election coming up, those very same taxpayers may decide just that.

A: The tender under which the contractor was appointed, which is an administra­tive function excluding any councillor interferen­ce, was done via open tender process, in line with the approved supply chain management regulation­s.

Newspapers in Afrikaans

Newspapers from South Africa