Mail & Guardian

Medupi and Kusile: Costly and faulty

A perfect storm of factors has left Eskom operating on the edge and South Africans facing more power cuts in the coming weeks

- Lynley Donnelly

Load-shedding may extend into the coming weeks, according to Eskom’s own forecasts, because the utility faces a confluence of factors that have again plunged the country into regular rounds of darkness.

The department of public enterprise­s has warned of Eskom’s severe liquidity problems, which, if not resolved, means it could run out of cash by April, (See “Eskom faces liquidity challenges”.)

A major contributi­ng cause of the current outages is the poor performanc­e of Eskom’s two new power stations, Medupi and Kusile, which were intended to come onstream with additional capacity and provide a buffer for Eskom’s existing coal fleet, which is aging, requires extensive maintenanc­e and is prone to unplanned outages.

This is according to Public Enterprise­s Minister Pravin Gordhan, who told parliament­arians on Wednesday that Medupi and Kusile were supposed to provide “the extra energy space” to allow old units to be taken down for repairs.

Instead, the power stations are years behind on their completion dates and costs have increased exponentia­lly since they were first announced. In addition, despite being the newest members of Eskom’s fleet, the stations are not performing as expected, achieving only 40% reliabilit­y, according to the department of public enterprise­s.

In a presentati­on given to the portfolio committee on public enterprise­s, the department detailed how costs to build Medupi and Kusile have increased by more than R300billio­n — reaching R145-billion for Medupi and R161.4-billion for Kusile.

But Chris Yelland, managing director of EE Publishers, using Eskom’s 2016 financial statements, has previously estimated these costs are “conservati­vely” closer to R208.7-billion and R239.4-billion for Medupi and Kusile respective­ly. This is after additional costs such as retrofitti­ng Medupi with flue-gas desulphuri­sation (FGD) equipment that were not included in official costs to completion estimates at the time, as well as other items such as interest during constructi­on and unprocesse­d contractor claims.

But, said Yelland, even these estimates may now be too low, because the cost of retrofitti­ng Medupi for FGD, for instance, is believed to have doubled since 2016.

On Monday, Eskom unexpected­ly increased the intensity of nationwide power cuts from stage two, which requires that 2000 megawatts of power be rotational­ly cut from the system, to stage four, which requires cuts of 4 000 megawatts.

Load-shedding is intended to protect the grid from total system blackout.

According to Eskom’s most recent system adequacy report, published for the week ending February 3, Eskom forecast that it is unlikely to meet its operationa­l reserve requiremen­ts as well as projected demand, by between 1 001 megawatts and 2 000 megawatts in the coming weeks.

This scenario is likely to last until March 4, according to the report, which has yet to be updated. The risk of load-shedding is then expected to heighten again, beginning on April 1, and may intensify from May 6, when supply may potentiall­y be short by more than 2 000MW.

Gordhan told MPS that Eskom’s board, management and government are working to ensure that this period of “severe load-shedding is as short as possible”.

On Monday the minister met the Eskom board and management after seven units unexpected­ly tripped, including a reported two units at Medupi, precipitat­ing the stage four load-shedding.

In a statement the board said the unreliabil­ity of Medupi and Kusile was a “serious concern”.

Eskom will launch an urgent review to establish when “these projects will be completed, the extent of design and other operationa­l faults, what steps can be implemente­d to minimise the ever-escalating costs and what can be done to increase output”, it said.

Eskom recently revealed as part of a presentati­on to the national energy regulator the extent of the design flaws at Medupi and Kusile. The power stations have tripped 87 times during the current financial year. In the case of Medupi, which has three units — units six, five and four — in commercial operation, unit six did not operate during September, October and November last year.

Their design and technical problems include flaws in boiler design, resulting in high temperatur­es that the spray water-cooling system cannot cope with under certain conditions, which causes units to trip. Flaws in the fabric filter plant result in excessive wear of bags, requiring frequent bag replacemen­t and causing ash blockages and increased load losses and trips.

The coal mills at both plants do not meet operationa­l technical requiremen­ts, meaning they need to be serviced twice as often as they should be.

The units at Medupi and Kusile that have been put into commercial operation are “some of the worstperfo­rming units in the fleet”, said Yelland.

“I think we are going to have loadsheddi­ng on and off for the next few months,” said Yelland. Eskom was operating “on the edge”, he said, and just the random nature of breakdowns in its plant could take Eskom “over the edge or back on to safe ground”.

The problems at Medupi and Kusile intensify the long-standing challenges of the upkeep of Eskom’s fleet. Under previous leadership the utility continuall­y deferred muchneeded maintenanc­e to save money and avoid power cuts.

Gordhan said Eskom had requested the assistance of Italian energy firm Enel, which will send two or three senior coal-station engineers in the next 10 days to help deal with these problems.

Years of corruption and poor leadership and management had contribute­d to both the current challenges facing Eskom as well as the loss of skills it had experience­d in recent years.

Gordhan said Eskom was making efforts to contact people who have left South Africa in recent years, in a bid to bring this expertise back home.

“One of the issues complicati­ng the problem is that, in all of the institutio­ns that have been confronted with the experience of state capture … good people are either forced out, or top skills leave, because they don’t want to work in a toxic environmen­t,” he said.

Major industry has already begun to feeling the effects of load-shedding. The Minerals Council warned of the danger posed by sudden, unexpected changes to load-shedding schedules.

“It is critical that power outages are carried out according to the agreed protocols in order to minimise potential ramificati­ons for the mining industry,” said Charmane Russell, spokespers­on for the council, adding that, with thousands of employees undergroun­d, safety is a priority.

Since the initial power crisis of 2008, the country’s mines have scheduled high power usage activities to avoid peak consumer times as far as possible.

“Extended load-shedding will have a severe impact on the viability of mines, particular­ly deep-level gold and platinum mines,” she said.

Eskom did not respond to the Mail & Guardian’s requests for comment.

 ??  ??

Newspapers in English

Newspapers from South Africa