Blunders put SANDF hospital in ICU

1 Military Hospital is in a serious state of disrepair and the report of a forensic investigat­ion into who is to blame for the mess remains under wraps

- Eunice Stoltz & Erika Gibson

The department of public works and the defence department are squabbling over who is to blame for the stalled R1.5-million bid in 2006 to upgrade the 1 Military Hospital at Thaba Tshwane, the main military area of the SANDF, in Pretoria.

A forensic investigat­ion report might shed light on who is to blame. But neither department provided answers regarding the whereabout­s of the report. The defence secretary, Sonto Kudjoe, has not received the full report after committing to share it with parliament. Nosiviwe Mapisanqak­ula, who was removed last week from her post as defence minister, was contacted about allegation­s that she was sitting on the report.

Meanwhile, 14 years of continued rotation of responsibi­lity between the two department­s to complete the 2006 refurbishm­ent project has thwarted contractor­s and consultant­s working on the project. There is little evidence of work having been done over the years.

“Since 2011 we have not put down a single brick,” said a source close to the refurbishm­ent project.

The once prestigiou­s 1 Military Hospital is a far cry from delivering its mandate of “providing combatread­y military health forces and an executive military health support service to the president of the Republic of South Africa”.

According to the defence budget for 2021-22, it had a budget R708millio­n and paid R261.7-million to private hospitals to outsource medical care because 1 Military Hospital could not do so.

Over 14 years, the responsibi­lity of upgrading the facility has been moved from the public works department to the defence department and now to the Developmen­t Bank of Southern Africa (DBSA).

The first and second floors of 1 Military Hospital — meant to have an emergency theatre, a pharmacy and a radiology section — stand abandoned because the leaking roof will be prioritise­d “as soon as the funds are available”, Major General Joseph Ledwaba, of the Defence

Works Formation, told parliament two months ago.

In 2006, the repair and maintenanc­e project was launched with the public works department as the implementi­ng agent. The project, according to the department’s responses in May to the portfolio committee, consisted of two contracts — building and civil works for R95-million and electrical and mechanical work for R108.8-million.

SSI Engineers and Environmen­tal Consultant­s, today called Royal Haskoningd­hv, was awarded the contract back in 2006. The company confirmed that the project duration was from 1 November 2006 to 30 November 2010. Riddled with delays, it stretched well into 2012.

According to the public works department, the defence department requested many changes to the scope of work, which could not be accommodat­ed under the contract.

“It was decided that another project be registered and that new consultant­s be appointed to deal with the new additions and requiremen­ts,” the public works department said. It dded that it was during the planning phase for the new project that the defence department was made the custodian of the repairs and maintenanc­e project, and took over in late 2014.

But the defence department had a different story to tell parliament on 3 June. It said the public works department was “not honouring its contractua­l terms” and that is why the defence department took over the project.

It was only in 2016 that the portfolio committee on defence and military veterans requested informatio­n on 1 Military Hospital after it noted “areas of concern on the procuremen­t processes that had caused a delay in the hospital meeting [its] targets”.

This happened after the defence department presented its performanc­e report to parliament where it noted outsourcin­g at its hospitals, because of inadequate of medical capacity, amounted to R450-million in the 2016-17 financial year.

In 2017, Major General Michael Ramantswan­a, the SANDF chief for military policy, strategy and planning, told the parliament’s joint standing committee on defence that a further R913730313 was needed to upgrade and refurbish 1 Military Hospital. Parliament was told that constructi­on was expected to start in September 2017, with a scheduled completion date of February 2019. This never happened.

Then the hospital’s leaking roof, which was one of the disputed consequenc­es of the initial constructi­on, leaked rainwater on the refurbishe­d Covid-19 floor, damaging some of the expensive equipment.

On 3 June it came to light in parliament that during this time the defence department had “conducted an investigat­ion into the constructi­on work at the hospital and the investigat­ion report had been finalised and executed”.

Lieutenant General Jabulani Mbuli, the SANDF’S chief of logistics, told parliament the report had been forwarded to the military police “to address the issues and deal with the implicated individual­s”.

Defence secretary Kudjoe added that the report contains “issues” concerning the public works department. She also listed a litany of defects which originated from the initial constructi­on work, and that there were legal issues with the public works department that had to be addressed.

“Specific recommenda­tions were made, including that the report had to be resubmitte­d for further investigat­ion by the South African Police Services.”

Kudjoe said the legal issues had to first be resolved before the defence department could continue the work because the majority of the consultant­s were appointed by the public works department, which was the implementi­ng agent 14 years ago.

She committed to send the report on the outcome of the forensic investigat­ion with the public works department, but by the end of July neither the department of public works nor the joint standing committee had received the report even after the public works department wrote to the defence department requesting it.

The Mail & Guardian understand­s that Kudjoe also said that she has not seen a summary of the report despite asking the now former SANDF chief General Solly Shoke for it.

Portfolio committee defence member MP Kobus Marais said he is submitting an applicatio­n through the Promotion of Access to Informatio­n Act to gain access to the report.

The M&G reached out to Kudjoe for comment but had not responded at the time of publicatio­n.

 ?? Photo: Delwyn Verasamy ?? Passing the buck: The department­s of defence and public works blame each other for the urgent remedial work that has not been done on1 Military Hospital in Pretoria since 2006.
Photo: Delwyn Verasamy Passing the buck: The department­s of defence and public works blame each other for the urgent remedial work that has not been done on1 Military Hospital in Pretoria since 2006.