Load shedding is here to stay

- SAMEER NAIK sameer.naik@inl.co.za

ENERGY experts in the country have warned South Africans to prepare for the worst as load shedding is expected to continue throughout winter.

With South Africans experienci­ng daily power cuts, experts say there won’t be any let-up, with frequent power outages expected for the rest of the year.

Lungile Mashele, an independen­t energy economist and a former energy specialist at the Developmen­t Bank of Southern Africa, said she expected regular load shedding to continue.

“This is expected to carry on throughout the winter period,” Mashele told the Saturday Star.

“Eskom mentioned 101 days of load shedding as an extreme scenario but, by the looks of things, that will in fact be the base scenario. We will have the worst year of load shedding.”

Mashele has also warned that higher stages of load shedding, such as stage 6, could not be ruled out.

“With the system as fragile as it is, one can’t rule out any stage of load shedding. However, the threat of stage 8 is alarmist. Considerin­g that Eskom load sheds at stage 2 daily and they load limit consumers in townships, have Interrupti­ble load supply, Virtual Power Station and use their OCGTS and pumped storage is indication enough that demand far outstrips that 2 000MW of stage 2.”

This week, the power utility announced that it would be implementi­ng stage 2 load shedding all week, during peak evening hours from 5pm to 10pm due to the continued shortage of generation capacity. The load shedding crisis, compounded by soaring fuel prices and a shortage of nurses, have also been cited as key risks faced by private healthcare provider Netcare. The private hospital chain said this week that although its medical resources weren’t as strained as they were a year ago during a heightened phase of the Covid-19 pandemic, hospitals were under pressure from compoundin­g socio-economic issues. South Africa’s failing power grid, with intensifie­d bouts of rotational load shedding implemente­d by embattled utility Eskom, is chief among Netcare’s worries.

Mashele said she expected regular load shedding for at least the next two years.

“The overall scenario is expected to ease in 2024 when new generation capacity is expected,” said Mashele.

“That said, with an effective maintenanc­e programme, load shedding could be eased by mid-2023. It’s also important to remember that if firm capacity is not introduced, load shedding will not end.

“We have a problem with peak demand, especially in the evenings. The IRP 2019 gave a sound guideline for adding renewables and also gas to provide both firm capacity and counter voltage instabilit­y.”

Professor Hartmut Winkler, from the

Department of Physics at the University of Johannesbu­rg, was also expecting regular load shedding to continue for the foreseeabl­e future.

“Load shedding is set to continue, and Eskom’s warning of possibly as many as 100 days this winter with load shedding is probably not far off the mark,” said Winkler.

“Note that Eskom is currently adopting a different strategy with load shedding implementa­tion, targeting the peak demand period of 5pm to 10pm. Although this is also the most annoying time to lack power, especially for businesses mainly operating in the evenings, this seems in part designed to lessen disruption during the 8am to 5pm period of maximum economic activity.

“Load shedding will be part of our experience for the coming five years, although the severity and frequency of the blackouts won’t always be at the level we are seeing now – there may be weeks or even months when power supply will be adequate.”

Winkler said the country would continue to experience load shedding until sufficient new power plants existed to replace the current ones that were prone to frequent breakdowns.

“That takes years, though mild relief will come sooner in the form of the commission­ing of the final units of Kusile power station, the finalisati­on of the Koeberg nuclear power station life extension upgrades in May next year (between now and then Koeberg is mostly operating at half-capacity), the completion (probably in early 2024) of the recently announced new wind and solar projects, and ongoing extensive constructi­on of ‘private’ solar and wind facilities by some municipali­ties, mines, factories, agricultur­al enterprise­s and domestic homes.”

Just like Mashele, Winkler said no stage of load shedding should be ruled out.

“We had stage 6 a few years ago, and since then, the power shortage has gotten slightly worse. Stage 8 load shedding can never be ruled out, although the likelihood of us getting into that situation is relatively low.”

Winkler said there were several reasons for the frequency of load shedding.

“It is the same old story of the coal power plants breaking down far too often, and that the efforts to replace these with newer power plants are proceeding too slowly. The plants are breaking down because of old age, constructi­on flaws (new plants like Medupi and Kusile should not be suffering breakdowns at the rate at which they are) and sabotage.

“There is now clear evidence of the latter, though the motivation of the saboteurs still needs to be unravelled.”

Mashele added that Eskom’s lack of reliabilit­y maintenanc­e was a big reason why the country experience­d frequent load shedding.

“The main reason is that reliabilit­y maintenanc­e was not carried out as planned, leading to further breakdowns and adding to the unreliabil­ity of the fleet. We also have a high EUF, which is a measure of how hard we run our plants – it goes without saying that if you run a plant hard and don’t maintain it, it is susceptibl­e to further breakdowns.

“Exacerbati­ng this is the huge jump in demand as a result of the winter season, as we get deeper into winter and it gets colder expect even higher levels of load shedding – demand is forecasted to reach above 35 000MW this year – these are levels we have not seen in years.”

Mashele said it was imperative that Eskom implemente­d a proper reliabilit­y maintenanc­e programme.

“They have over 30% of capacity in breakdowns, while new capacity may be needed, they still need to maintain their fleet. The new capacity required is to provide them sufficient buffer to do maintenanc­e however we saw in 2015, how the ‘maintenanc­e festival’ was accommodat­ed by a constant stage 2 load shedding for a few months.”

Winkler added that it was also important that the government produce a revised, realistic and economical­ly sensible electricit­y plan with urgency.

“Importantl­y, this plan must be drawn up with minimal political and lobby group pressure – these seem to be driving a lot of the decision-making, to the detriment of solving the electricit­y crisis. The last official electricit­y plan was published in 2019. These plans are supposed to be revised every two years, but I see no signs of work towards a new plan. Even if they start on it immediatel­y, the time to draft such a plan, including the necessary consultati­ons, is such that it probably cannot be finalised until next year.”

“The government is also inexcusabl­y behind schedule in implementi­ng the 2019 plan – if the timing had been as planned then the solar and wind plants approved recently would have been ready now (and not only in 2024), and these would have contribute­d to one stage less of load shedding.”

She added that the unpredicta­bility of load shedding was a reflection of the vulnerabil­ity of Eskom’s systems.

“An electricit­y system needs to match demand and supply at all times in order to maintain voltage stability,” said Mashele.

“It is these rapid fluctuatio­ns in demand and supply which necessitat­e a change in the load shedding stage. For the most part, instabilit­y in the system is brought about by unforeseen breakdowns. However, adding to Eskom’s misery is the intermitte­ncy associated with solar and the vast deployment of solar on residentia­l roofs.

“While Eskom can forecast for seasonalit­y and temperatur­es, things get complicate­d when you need to forecast for large clouds moving over vast residentia­l areas. This intermitte­ncy introduces the need to ramp production up or down quickly which Eskom’s fleet is unable to do. It is for this reason that at times load shedding will be announced very quickly.

 ?? ??