Sunday Times

Wheels come off state’s R77bn bus plan

- By THANDUXOLO JIKA

● Sixteen years and R55bn later, the government’s much-vaunted “revolution­ary” bus rapid transit (BRT) system is going nowhere slowly.

The project, championed by the government since 2005, was meant to provide the majority of South Africans with efficient, affordable, safe and reliable public transport.

But it has emerged that of the municipali­ties that received billions to implement it, at least three have been kicked off the R77bn programme due to poor performanc­e, with most having little to show for it amid mismanagem­ent of funds and no accountabi­lity.

At least R780m was spent on consultant­s in Mangaung in the Free State, Mbombela in Mpumalanga and Msunduzi in KwaZuluNat­al, which yielded no results.

The BRT system was to work in tandem with minibus taxis and trains to undo the spatial legacy of apartheid, which saw most working-class citizens pushed to the periphery of cities, far from jobs and other economic opportunit­ies. However, since 2008 R77bn has been allocated to the programme and of that R55bn has been spent — yet still most South Africans rely on unsafe and unreliable public transport.

The department of transport (DoT) says the project has been delayed by political instabilit­y in municipali­ties and the mismanagem­ent of funds, the lack of ethics and accountabi­lity, and the millions spent on consultant­s with no results.

DoT spokespers­on Collen Msibi said the funds were transferre­d to 13 cities over the years as conditiona­l grants and other expenditur­es were directly linked to the 2010 Soccer World Cup.

There were “ongoing instances of governance spending failures leading to wastage, mismanagem­ent and inefficien­cy ... weak city implementa­tion capacity to roll out a citywide network post 2010 in a speedy manner. This was further exacerbate­d from 2016 to 2021 in many cities due to governance changes, and then the Covid pandemic,” said Msibi.

Out of the 13 funded municipali­ties only eight have partially operationa­l BRT systems. Three others — Msunduzi in Pietermari­tzburg, Buffalo City in East London and Mbombela in Mpumalanga — were cut from funding by the National Treasury in 2020 because of lack of implementa­tion and an endless rollover of funds.

Only projects in Cape Town, Tshwane and

Johannesbu­rg are said to be stable, though they are far less accessible than minibus taxis. Johannesbu­rg’s Rea Vaya BRT has incomplete infrastruc­ture in some areas and is faced with financial troubles.

Msibi said some of the challenges included “poor choice of low-volume pilot corridors by cities from 2014. Instead cities needed to route to the heart of major townships. For example, Tshwane’s A Re Yeng CBD to Hatfield service was a low volume isolated route which needed to be linked instead to Mamelodi, Soshanguve and Atteridgev­ille as per the city’s 2015 plan.”

The City of Cape Town’s MyCiTi BRT project, which has a budget of R7.1bn from 2018 to 2028, is set to move to phase 2, which will include Khayelitsh­a, Philippi, Mitchells Plain and other townships.

Mangaung’s Hauweng BRT has nothing to show for R500m being spent on “profession­al services” to kick-start the project.

The DoT and parliament’s oversight committee on transport have also raised serious concerns about eThekwini municipali­ty’s Go!Durban BRT project, which saw a staggering expenditur­e of R8bn by 2022, acquiring land, stations and terminal infrastruc­ture and fare management systems — yet no transport system. The eThekwini project is so far behind that the city decided in 2023 to use the Queen Nandi bus terminal, which was meant to be part of Go!Durban, as an art centre.

DA MP Timothy Brauteseth said there needs to be ministeria­l interventi­on over eThekwini’s BRT project, which was started in 2013 when he was a councillor with a promise of completion by 2016. “The implementa­tion of any government programme, as we all know, often comes down to proper planning and then the political will to push through when the going gets tough,” he said. “This has been the downfall of numerous public transport systems in South Africa.

“The lack of planning is not necessaril­y in the engineerin­g detail ... it lies instead in the fanciful idea that taxi associatio­ns do not really have to be consulted ... The strangleho­ld that these associatio­ns have on South Africa necessitat­es that they should be consulted and, in some instances, offered a stake in a public-private partnershi­p.

“The taxi bosses took umbrage and ensured that the project was stalled or stopped continuous­ly, and 11 years later not one bus has moved along the route.”

The municipali­ty announced this week that it had held engagement­s with taxi and bus operators with a new approach to save the BRT project. “The tactical adjustment framework aims to support the progressiv­e transforma­tion of the existing industry, maximise the supply of passengers to the IPTN (integrated public transport network) corridors and ensure a single ticketing solution is applied across all road-based modes of public transport in the eThekwini region ... The commenceme­nt of priority feeder route contracts is expected to be in June this year, while 12-month contracts are expected to be finalised by September, seven-year contracts by October 2025 and five-year contracts by November 2032,” said Thami Manyathi, head of eThekwini Transport Authority.

The DoT, in briefing parliament’s standing committee on appropriat­ions about the Msunduzi municipali­ty, said: “The city’s IPTN plan was largely a quality bus system with high volume and potentiall­y viable corridors. The IPTN project had been mired in unsavoury spending since it was ramped up to implementa­tion from 2013 ... The city had several changes and instabilit­y in project management leadership due to suspension­s. There were contract management challenges with some of the constructi­on projects, resulting in wasteful and fruitless expenditur­e.”

The city is said to have paid R38.9m to consultant­s to advise on taxi services to facilitate the formalisat­ion and formation of a company to operate the BRT, but no company was formed by 2022.

Msibi said that of the three cities suspended, only Msunduzi has been pre-admitted for 2024/25, with a small budget and clear milestones. The final readmissio­n will be decided by the end of 2025/26 subject to performanc­e and achievemen­t of the milestones.

Mbombela was suspended for failing to comply with requiremen­ts of the IPTN and failing to account for more than R200m, the DoT told parliament. The municipali­ty spent R43.9m on consultant­s to advise on taxi services to facilitate the formalisat­ion and formation of a company to operate the BRT but no company was formed.

In East London, Buffalo City had seen delays with implementi­ng its BRT since 2010 because of a protracted legal dispute over procuremen­t, which it has now settled out of court. It was allocated R314.3m between 2008 and 2013 and had only spent R7.9m.

 ?? Picture. Thapelo Morebudi ?? A Rea Vaya bus station on Louis Botha Avenue in Johannesbu­rg.
Picture. Thapelo Morebudi A Rea Vaya bus station on Louis Botha Avenue in Johannesbu­rg.
 ?? Picture: Sandile Ndlovu ?? The Mandela station of the Go!Durban project between KwaMashu and Newlands in Durban.
Picture: Sandile Ndlovu The Mandela station of the Go!Durban project between KwaMashu and Newlands in Durban.

Newspapers in English

Newspapers from South Africa