Sunday Tribune

N2 road saga finally in court

Following 16 years of civil action by the local communitie­s, a judicial review of Sanral’s Wild Coast plan is under way

- ROY COKAYNE roy.cokayne@inl.co.za

THE judicial review of the SA National Road Agency’s (Sanral) realignmen­t of the N2 along the Pondoland Wild Coast has been welcomed by the Organisati­on Undoing Tax Abuse (Outa).

The organisati­on said the review followed civil action over 16 years by the local community, which had tirelessly resisted Sanral’s bullying tactics.

The case commenced in the Pretoria High Court last week before Judge Cynthia Pretorius.

Wayne Duvenage, chief executive of Outa, said the long-awaited review of the environmen­tal authorisat­ion on what appeared to be an extremely unpopular scheme was long overdue and taking place at a time when the country could hardly afford further wasteful expenditur­e.

Duvenage was hopeful the case would highlight the serious consequenc­es arising from the lack of meaningful community engagement and expose the real beneficiar­ies of this costly decision.

However, Vusi Mona, a spokespers­on for Sanral, highlighte­d that the.first and second respondent­s in the case were actually the Minister and Department of Environmen­tal Affairs, and Sanral the third respondent.

Mona said the applicants’ lawyers were seeking to overturn the positive record of decision (ROD) granted by the Department of Environmen­tal Affairs for the project and not seeking to amend the route.

Outa added it had noted the statement by Richard Spoor, the attorney for the applicant, Sinegugu Zukulu, that “regardless of the outcome, the project is headed for disaster at huge cost to the taxpayer” and that Sanral’s mishandlin­g of local communitie­s was “at the heart of the matter” because it had been “arrogant, contemptuo­us, manipulati­ve and dishonest in their dealings with them”.

Duvenage said this was history repeating itself.

“Just as we saw on the Gauteng e-toll matter, it would appear that Sanral has overlooked its obligation­s to Section 195 of the Constituti­on, which requires it to promote ‘a high standard of profession­al ethics’ and ‘respond to people’s needs’ and ‘provide the public with timely accessible and accurate informatio­n’,” he said.

Duvenage was also critical of Sanral’s “attrition through lawfare” tactics of bringing interlocut­ory applicatio­ns, which had delayed the commenceme­nt of the proceeding­s and been compounded by a display of arrogance in Sanral’s decision to start constructi­on of the access roads to the sites before the judge had ruled if the scheme was lawful or not.

“Fortunatel­y, Sanral’s attempts to squash the case have failed and the beleaguere­d SOE (state-owned enterprise) now faces the prospect of having to halt the scheme if the High Court finds in favour of Zukulu and the community residents.”

Duvenage claimed Sinegugu and the community had to work out exactly where the proposed new short cut route would be located because Sanral refused to make that informatio­n available.

Mona said the court case to challenge the granting of the ROD was only brought in 2012 and the first interlocut­ory case was for the court to condone that the challenge was brought well beyond the 180 days allowed in law.

He said Sanral had already started constructi­on of the N2 Wild Coast Road when the court challenge was brought and consistent­ly communicat­ed with the lawyers representi­ng the applicants that it would continue to construct the road unless the applicants obtained a court order to halt the project.

The applicants had never sought such a court order, he said.

Mona stressed the environmen­tal impact assessment (EIA) was conducted in full compliance with the National Environmen­tal Management Act and all relevant stakeholde­rs in the umgungundl­ovu community were engaged through a number of different channels during both the original 2001 and subsequent 2007 EIA processes.

He said Sanral continued to conduct extensive community and stakeholde­r consultati­on.

Mona said an independen­t 2015 Human Sciences Research Council (HSRC) survey found 98.8 percent support level for the project from respondent­s across Pondoland.

He claimed opposition to the project was far from widespread and limited to a relatively small number of residents in the Xolobeni area of Mbizana who incorrectl­y had directly linked the road to the proposed and controvers­ial Xolobeni sand dune mine.

Mona said the Amadiba Traditiona­l Authority that sat above the umgungundl­ovu sub-authority and represente­d the entire Amadiba tribe had given its full support for the project as had all the elected local councillor­s.

“Outa’s contention of widespread local opposition to the project is therefore devoid of fact,” he said.

Mona confirmed constructi­on on the Mtentu bridge was currently suspended due to protest action and labelled as “untrue” Outa’s claim that Sinegugu and the community had to work out exactly where the proposed new shortcut route would be located.

The route was widely published on various maps, he said.

Just as we saw on the Gauteng e-toll matter… Sanral has overlooked its constituti­onal obligation­s

Wayne Duvenhage

 ??  ??
 ??  ??

Newspapers in English

Newspapers from South Africa