Talk of the Town

Water tower nearly done

EC officials inspect R57m project, and R6m paving

- FAITH QINGA

Representa­tives from the Eastern Cape Premier’s Office, accompanie­d by members of the provincial legislatur­e, conducted an oversight visit at the Thornhill 2.6ML elevated tower and West Beach Drive on Monday.

The officials started with a drive along West Beach Drive, where the paving was completed in 2019, and then proceeded to the Thornhill water tower.

There they met with Mamlambo Constructi­on’s site manager, Bevan Kashagen, to inspect the project’s progress.

The oversight visit came after R63m in funding from the premier’s offfice from the Small Town Revitalisa­tion Grant was allocated to Ndlambe Municipali­ty in the 2018/2019 financial year.

Of that, R6m went to paving West Beach Drive and R57m was used for the elevated water tower and pump station.

The West Beach Drive paving project was completed within the deadline.

During the visit, Kashagen confirmed that the elevated tower project was delayed but was expected to be completed by the end of June.

According to Kashagen, the change of ownership of the company and a subsequent legal battle had affected the timeframe to complete the tower project.

The tower was supposed to be complete by March and because of the challenges with the company takeover, they were then given a three-month extension by the municipali­ty to complete the project.

Director of infrastruc­ture, Dr Noluthando Vithi, said: “There was interventi­on from the office of the premier in terms of how they should be taking the project forward, because we didn’t want to terminate the contract when they’re only 3% away from completion.”

The 2.1km West Beach Drive paving was done by two SMMEs.

According to Vithi, this created work opportunit­ies for Ndlambe residents.

“We didn’t hire a big contractor for the beach road because we wanted to develop small enterprise­s so they can develop skills.

“That also [provided] work opportunit­ies for the people of this community,” Vithi said.

Kashagen confirmed that skills transfer had taken place during the project, with concrete work and steel fixing done by SMMEs.

He said the project was close to completion, with only 3% of the work left to be done.

Vithi further confirmed that once the Thornhill 2.6ML elevated tower was complete, it would be enough to supply residents in both Nemato Township and Thornhill.

Vithi also said the pipelines to the Sarel Hayward Dam were now fully operationa­l and this meant the amount of water pumped into Port Alfred’s main supply dam would increase.

 ?? Picture: TK MTIKI ?? CRUCIAL INFRASTRUC­TURE: Ndlambe municipal manager, advocate Rolly Dumezweni, Ndlambe director of infrastruc­ture, Dr Noluthando Vithi, CFO in the Office of the Premier (former programme manager for the Small Towns Revitalisa­tion Project) Liziwe Ndzima, MPLs Makhaya Twabu and Zinziswa Rabe, engineerin­g consultant Aubrey Gelderblom, MPL Nqaba Bhanga, OTP general manager Busisiwe Khumalo, and monitoring and evaluation manager, Dumisani Feni, during an oversight visit to the 2.6 megalitre elevated tower on Monday, in Thornhill, in Port Allfred. The tower is close to being completed, with 3% of the work left to be done
Picture: TK MTIKI CRUCIAL INFRASTRUC­TURE: Ndlambe municipal manager, advocate Rolly Dumezweni, Ndlambe director of infrastruc­ture, Dr Noluthando Vithi, CFO in the Office of the Premier (former programme manager for the Small Towns Revitalisa­tion Project) Liziwe Ndzima, MPLs Makhaya Twabu and Zinziswa Rabe, engineerin­g consultant Aubrey Gelderblom, MPL Nqaba Bhanga, OTP general manager Busisiwe Khumalo, and monitoring and evaluation manager, Dumisani Feni, during an oversight visit to the 2.6 megalitre elevated tower on Monday, in Thornhill, in Port Allfred. The tower is close to being completed, with 3% of the work left to be done

Newspapers in English

Newspapers from South Africa