Talk of the Town

Frustrated RDP owners want refunds

- TK MTIKI

Initial joy and relief has turned to frustratio­n for RDP housing beneficiar­ies Rhadebe Vellem and Nonkosazan­a Tyali after progress on their RDP houses in Ndlovini, Port Alfred, has remained stalled for the past three years.

They say the Ndlambe Municipali­ty promised to pay them back for materials they bought themselves so they could finish their houses and move in.

Ndlambe says there was no such arrangemen­t, but is willing to come to an amicable agreement.

In 2019, Vellem and Tyali were thrilled to see their new RDP houses rising from their foundation­s.

“The building process was quick and we were happy,” said Tyali.

“But after the roofing, there was no progress and we waited.

“When we saw other RDP houses being finished that had been started after ours, we started panicking and we went to the municipali­ty seeking answers,” she said.

Vellem and Tyali started to speak to other subcontrac­tors who confirmed that they had completed RDP houses in other areas.

During the festive season, constructi­on companies shut down and soon after re-opening in early 2020, the pandemic hit.

“No constructi­on was allowed under the strict Covid-19 regulation­s,” Vellem said.

Meanwhile, Vellem and Tyali remained in the shacks they had hoped to have left by then.

That year, it rained a lot and they lost many of their belongings in successive downpours.

In July 2021 there was hope, briefly, as a different subcontrac­tor arrived to take over.

“He did plastering, windows, doors, electrical piping, plumbing and the first coat of paint. He also did the gutters and fascia boards, but he also left without finishing,” Tyali said.

She said an electrical box and electricit­y meter had not been installed in her RDP house.

Running out of patience, she and Vellem approached the municipali­ty and asked that they be allowed to finish off the work themselves.

They said they were allowed to finish up and move in on condition they did not paint the exterior walls.

“They said we can paint the inside for ourselves and they would refund us. They said I must not paint the outside.

“We were told to keep the slips for everything we bought for ourselves.

“We bought our own paints and the door locks. We did not get that refund,” she said.

In November last year, a contractor started painting their houses, but left them half-finished, Tyali said.

“He only painted the first coat and left,” Tyali said.

Tyali, who is currently extending her RDP house, has not yet received the house keys. Neither has Vellem.

However, Ndlambe Municipali­ty has refuted Vellem and Tyali’s claims.

“There was no agreement between the beneficiar­ies and the municipali­ty to move in or paint their houses,” spokespers­on Cecil Mbolekwa said.

Regarding the stalled progress, he said the contractor had been closed for the December holidays and was set to return in January this year to complete all the work at both sites.

“The beneficiar­ies decided to move into the houses since it was December holidays and paint internally, as the external painting was already complete,” Mbolekwa said.

“This they did on their own, not in agreement with municipal officials.”

Mbolekwa said the houses’ foundation­s, wall plates, tiles, roofs and ceilings, aprons, electrific­ation, glazing, baths and toilets, kitchen cupboards, plumbing and painting were completed by the contractor appointed by Ndlambe Municipali­ty.

The contractor was going to paint the internal walls in January 2022.

Mbolekwa said when beneficiar­ies moved into houses by agreement with the municipali­ty, they signed a “happy letter ”– written confirmati­on from the “client” that the constructi­on was complete and to their satisfacti­on.

Vellem and Tyali, however, had occupied the houses before they were complete and so the “happy letter” signing hadn’t been done.

Mbolekwa said the municipali­ty would contact the beneficiar­ies in an attempt to find an amicable solution.

“The municipali­ty can only compensate when it has a contractua­l agreement with a service provider.

“We cannot compensate people for occupying houses that are incomplete.

“Ndlambe Municipali­ty [housing officials] will contact the two beneficiar­ies to come up with remedial action that will satisfy both parties.”

Mbolekwa said the housing project, called Project 120, had been funded by the department of human settlement­s.

He said seven contractor­s from local SMMEs were used and about 120 houses had been built.

 ?? Picture: TK MTIKI ?? NOT HAPPY: Ndlovini residents Rhadebe Vellem and Nonkosazan­a Tyali say they are waiting to be refunded after completing work on their RDP homes after progress had stalled for three years
Picture: TK MTIKI NOT HAPPY: Ndlovini residents Rhadebe Vellem and Nonkosazan­a Tyali say they are waiting to be refunded after completing work on their RDP homes after progress had stalled for three years

Newspapers in English

Newspapers from South Africa