The Citizen (KZN)

Eskom’s millstones

MEDUPI, KUSILE: COAL-FIRED POWER STATIONS’ PRICE TAGS BALLOON

-

Flagship projects were supposed to have been completed by 2015.

SA’s economy was roaring along in 2007 on the back of the global commoditie­s boom, when power shortages struck, bringing mines and smelters to a halt.

The then president, Thabo Mbeki, publicly apologised for prevaricat­ing about adding generation capacity, despite repeated warnings that supply was constraine­d, and state power utility Eskom swiftly opened the spending taps.

The botched implementa­tion of the expansion plan has haunted the country ever since.

Eskom in 2007 alone approved 13 projects worth more than R200 billion that it said would boost electricit­y output by 56% by 2017.

The flagships were two mammoth coal-fired power stations, Medupi and Project Bravo, that were expected to be finished by 2015 at a total cost of R163.2 billion.

Instead of resolving the energy shortfall, the plants have been textbook studies on how not to execute large infrastruc­ture projects. Medupi’s completion date has been pushed out until next year or 2021 and Kusile, as Bravo is now called, is scheduled for 2023.

The delays have resulted in months of rolling blackouts, an economy in deep trouble and a huge headache for President Cyril Ramaphosa.

Mike Rossouw was appointed as an independen­t consultant to Eskom in 2014 to advise it on how to address its constructi­on challenges. He said: “They needed to call a halt to the whole project and do a reset – to go back into the contracts and the design and engineerin­g. They never did that ... and the consequenc­es are there for all to see.”

Meanwhile, the anticipate­d price tag has ballooned to R451 billion, including the costs of interest during constructi­on and fitting the plants with equipment needed to meet environmen­tal standards.

That equates to Eskom’s entire current debt, a burden that’s left it unsustaina­ble and reliant on a three-year, R128 billion government bailout to remain solvent.

The utility now concedes multiple failings that led to cost overruns and delays, including inadequate planning and front-end engineerin­g developmen­t, plus ineffectiv­e contractin­g strategy, execution and oversight.

Contractor­s performed poorly and incurred limited penalties, while strikes and demonstrat­ions compounded the implementa­tion woes. Turnover at the top – the company has had 11 permanent and acting chief executives since constructi­on began – didn’t help.

Eskom also assumed much of the risk of developing Medupi and Kusile when it decided to coordinate the projects, rather than appointing an outsider to oversee engineerin­g, procuremen­t and constructi­on – a common practice in plant developmen­t.

“The SA market at the time was not ready for a single contractor to handle the onerous risk of executing a project of this complexity and magnitude,” Eskom said in an e-mailed reply to questions.

The company also wanted to develop skills and create jobs by bringing in small and medium-sized contractor­s, it said. – Bloomberg

 ?? Picture: Bloomberg ?? DELAYED. The Kusile coal-fired power station in Mpumalanga was originally scheduled for completion in 2015. The date has now been pushed out to 2023.
Picture: Bloomberg DELAYED. The Kusile coal-fired power station in Mpumalanga was originally scheduled for completion in 2015. The date has now been pushed out to 2023.

Newspapers in English

Newspapers from South Africa