The Citizen (KZN)

Over R1bn loss for Stefanutti Stocks

PROVISIONS: RAISES R1.18BN FOR FUTURE COSTS

- Roy Cokayne

Company and Eskom are in claims resolution process.

JSE-listed Stefanutti Stocks, which is involved in a dispute with Eskom, has raised R1.183 billion in provisions for future costs, project losses and a tax liability in Kenya.

The provisions include a further R462 million provision for potential unrecovera­ble monthly measured works to complete a controvers­ial building project at the Kusile Power Station.

This is in addition to the provision of R263 million raised in February last year for potential unrecovera­ble preliminar­y and general costs at Kusile.

Apart from the provision for future costs at Kusile, Stefanutti Stocks has also made:

R331 million in specific provisions for slow-paying trade receivable­s;

A R294 million provision for specific project losses;

A R53 million provision for impairment of goodwill; and

A R43 million provision for a tax liability in Kenya.

These provisions contribute­d towards Stefanutti Stocks reporting a loss of more than R1 billion in the year to end-February.

CEO Russell Crawford said the substantia­l increase of internal funding for this Kusile project increased the group’s total funding requiremen­t from R400 million to about R986 million, excluding the impact of Covid-19.

Crawford attributed this to Eskom adopting “an adverse approach to authorisin­g certificat­es for work done on the Kusile building project”.

Alleged overpaymen­t

Eskom alleged in a briefing document dated 10 June that it overpaid an estimated R1 billion to a Stefanutti Stocks-Basil Read (SSBR) joint venture for the Package 16 building project and the Stefanutti Stocks Izazi joint venture for Package 28.

This overpaymen­t forms part of the almost R4 billion alleged overpaymen­t by Eskom to various contractor­s at the Kusile power station. The Eskom briefing document said investigat­ions by the Special Investigat­ions Unit (SIU), Bowman Gilfillan and Eskom into these overpaymen­ts to contractor­s at Kusile is ongoing.

Stefanutti Stocks earlier emphatical­ly denied it had been overpaid by Eskom and claimed the SSBR joint venture is owed additional amounts for work done since December 2018 and for which payments have been withheld. Package 16 comprised 81 buildings, including the unit auxiliary bays, at Kusile.

Crawford said the group believed there should be a future payout from Eskom.

He said Stefanutti Stocks and Eskom are in a claims resolution process where each party is employing independen­t experts to evaluate the causes of delays and the quantum of claims.

Crawford said Package 16 involved “a complex claim” and it will take while to be finalised.

In regard to the Package 28 contract awarded to the Stefanutti Stocks Izazi joint venture, Crawford said this was a much smaller and much easier project.

“They [Eskom] terminated the project because they could not give us access. We are just finalising all the commercial issues. It has gone to adjudicati­on and we should have some form of ruling by the end of this year,” he said.

Results

Stefanutti Stocks on Thursday reported a 13% decline in contract revenue to R8.6 billion in the year to February from R9.9 billion in the previous year.

The operating loss before investment income skyrockete­d by 554% to R1.03 billion from the prior loss of R158 million.

It reported a headline loss per share of 622.48 cents compared to the 70.12 cent loss in the prior year. The group’s order book stands at R8.5 billion, of which R4.2 billion relates to work beyond South Africa’s borders.

 ?? Picture: Bloomberg ?? CONFLICT. The group says Eskom has adopted an ‘adverse approach’ to authorisin­g certificat­es for work done at Kusile.
Picture: Bloomberg CONFLICT. The group says Eskom has adopted an ‘adverse approach’ to authorisin­g certificat­es for work done at Kusile.

Newspapers in English

Newspapers from South Africa