The Herald (South Africa)

R800m East Cape road project runs into problems

- Sikho Ntshobane

Phase two of one of the biggest road constructi­on projects in the Eastern Cape, which will culminate in the tarring of a 52km gravel stretch which in 2015 claimed the lives of 36 people in a horrific bus accident, has run into problems just months after it started.

Last week, several small subcontrac­tors from Dutywa, Xhora and Willowvale in the Mbhashe municipal area alleged they were being exploited by the main contractor, WBHO Constructi­on.

Attempts to obtain comment from the constructi­on company, one of the largest in SA, were not successful.

Phase two of the project involves the tarring of a 15.5km of the notorious gravel route from Willowvale to Msengeni Junction.

In 2020, then transport MEC Weziwe Tikana-Gxothiwe announced WBHO had been awarded a tender for upgrading the gravel road between Willowvale and the Dwesa Beach.

The total project was valued at R800m and constructi­on work was divided into four phases. The first phase involved the repairing of roads in Willowvale and the constructi­on of a bypass, and this has been completed.

Some of the subcontrac­tors working on phase two, who spoke on condition of anonymity, said their companies were appointed and told to tender according to the packages available on the tender.

“We are new in the industry. From the start, they [main contractor] declined to accept our proposed rates and came up with their own rates, and if we did not accept them, it was a question of take it or leave it.

“Out of desperatio­n we accepted because we wanted to work.”

The contracts they signed when they started work in November were valid for only two months and had lapsed.

However, they were told verbally to continue working, the subcontrac­tor said.

He said the contractor had also also provided them with some working materials, which were later deducted from their pay.

This left many of them without enough money to pay their workers or take care of their families.

They said they had tried to reason with the contractor, but to no avail.

In May and August they even resorted to closing the site, chasing the main contractor away.

Another subcontrac­tor had asked newly appointed transport MEC Xolile Nqatha for help.

A WBHO director said they were not allowed to discuss the contract with the media due to confidenti­ality issues.

Nqatha, meanwhile, said he had asked for a full report from his head of department.

Newspapers in English

Newspapers from South Africa