The Mercury

City looks at ‘double’ contract

- Sihle Manda, Kamini Padayachee and Zohra Mohamed Teke

AN ETHEKWINI Municipali­ty housing contract, which saw two companies being paid close to R30 million for what appeared to be doing the same work, could see two controvers­ial former senior municipal officials, Cogi Pather and Derrick Naidoo, facing a possible criminal investigat­ion.

At an exco meeting yesterday it was revealed that the city’s integrity and investigat­ions unit (CIIU) had recommende­d that the city lodge a criminal case to find out why the second contract amount was almost equal to the first one, which had been near completion when taken over.

But while Pather was unavailabl­e for comment, Naidoo strongly rebutted the accusation­s. He pointed out that “the magnitude of the poor workmanshi­p we were dealt with” by the first contractor drove the costs needed to fix the buildings. (See his full response alongside.)

Glaring questions have also been raised about why the city has now agreed to pay the failing contractor a further R2.4 million. This is despite the city’s winning a court case against the company.

Pather, the former housing head, and Naidoo, the deputy city manager for infrastruc­ture, were at the helm of the city’s housing department when it awarded an R18 million contract to DKS Holdings to build houses for the Umlazi Glebelands Hostel Complex in 2005. The two are no longer with the municipali­ty. They were named in the Manase report on fraud and corruption, but both denied any wrongdoing.

At Glebelands the city had found defects in the work carried out by DKS, including doors cut into irregular shapes and narrow passages. DKS was asked to submit a programme of how the work was going to be completed and corrected.

When this was not done, the contract was terminated, with DKS having already been paid R15.3 million. DKS went to court challengin­g the cancellati­on of the contract and the court ruled in the city’s favour.

Mochu Civils was then awarded a contract for remedial work, costing R14.2 million.

The municipali­ty also withheld R2.4 million from DKS in 2007 to cover remedial work.

According to the CIIU report, DKS director Mandla Khumalo sued for damages but abandoned this because of financial problems.

He then made representa­tions to mayor James Nxumalo and the city’s municipal public accounts committee, in June last year, for an out-of-court settlement.

The CIIU was mandated to investigat­e the matter and concluded it in January this year. It was only submitted to exco yesterday.

The municipali­ty said in a statement yesterday that exco had recommende­d that DKS be paid, as the company was in financial difficulti­es and facing liquidatio­n.

“In an effort to ensure administra­tive fairness, the CIIU recommende­d the refund of the retention and sureties to the contractor as well as the outstandin­g payments to the contractor resulting from invoices that was submitted but not paid.”

According to the CIIU report, its investigat­ion sought “to establish reasons for the project appearing to have huge defects even though it was deemed 95% complete and payment effected in this regard”.

The report says: “If indeed there was poor workmanshi­p by DKS, our former officials as well as the outsourced management team were party to fraud in that they would have misled the municipali­ty into believing that value for money was received.”

The report also questioned why the second contractor was paid close to the initial contract price for remedial work.

The report said that Mochu Civils appeared to have been appointed to do a complete revisit of the project.

The investigat­ion also sought to “to establish the apparent poor performanc­e by the profession­al team which led to the council’s interest not being safeguarde­d”. Profession­als and city staff were also to be interrogat­ed by the CIIU, but it said Pather and Naidoo were not forthcomin­g with the investigat­ors.

Approached for comment, former municipal manager Michael Sutcliffe questioned why the municipali­ty had agreed to an out-ofcourt settlement with DKS after a ruling in the municipali­ty’s favour.

He did not want to comment on the recommenda­tion of a criminal investigat­ion into the award of the tender to the second contractor.

However, he said that often when remedial work had to be done it led to a structure having to be demolished if the initial work had not been up to standard.

 ??  ?? NAIDOO
NAIDOO
 ??  ?? PATHER
PATHER

Newspapers in English

Newspapers from South Africa