The Mercury

Delayed caisson repairs leave ship repair contractor­s high and dry

-

THE vexing matter of the availabili­ty of Durban’s dry dock is again in the news, with Transnet National Ports Authority (TNPA) announcing that the completion date has been brought forward by one month to November 25.

Readers will recall that the dock has been unavailabl­e to general shipping for a lengthy period of this year.

This was a result, firstly, of the several months that the SA Navy frigate, SAS Amatola, spent occupying the dock. More recently it has been the overdue repairs to one of the dock’s two caissons, which is now stretching to three months of unavailabi­lity.

The caissons, or lock gates, are the big pieces of equipment that form the gate used to open and close the dock. The Durban dock has two of them, one upfront at the dock entrance and the other which is used to divide the dry dock into two separate compartmen­ts, thus allowing two ships to be docked and repaired independen­tly of each other.

The outer dock was declared faulty several years ago and was replaced by the inner dock, thus turning the dry dock into a single chamber.

Contract

It is the damaged outer gate that is now undergoing repair.

The ports authority issued a contract to Durban company Channel Constructi­on to undertake the overhaul and extensive repair of the outer caisson. The original contract called for a two-month nonoperati­onal period in August and September, followed by a partly operationa­l period in October and November. That schedule was thrown out when the hospital ship, Africa Mercy, which was the last vessel to dock before the repair, encountere­d additional repairs that necessitat­ed bringing spares from Europe, causing a two-week delay. As a result, the contract on the dry dock and gate only commenced on August 20, 2015, 21 days late.

“This delayed start impacted on the erection of scaffoldin­g and the appointed contractor’s occupation of the dock, which had a direct knock-on effect on critical path activities and threatened to push the completion date of the project to December 24, 2015. Due to the time lost… it became apparent the contractor’s methodolog­y would need to be changed,” said port manager Moshe Motlohi.

“We have tried to minimise any further impact on the ship repair industry by taking measures to bring the project completion date forward by a month, although the dock’s non-operationa­l period has been extended from late October to also end on November 25, 2015.”

But Motlohi said that while the revised methodolog­y should enable an earlier project completion date, it also posed what he described as serious risks associated with docking a vessel whilst the project was in progress. Ship repairers had wanted to be able to dock ships from early November by sharing the dock with the caisson but TNPA has ruled this out saying it was too dangerous. As a result dry dock bookings are only being accepted for dates after November 25, 2015.

Ship repair contractor­s say they had been assured the dock would be available from the end of October in a partly operationa­l fashion, as per the original announceme­nt, a date which Transnet has now postponed by a month on grounds of safety. They claim contracts worth millions of dollars for ship repair have been lost or turned away.

They say it would have been possible to dock a ship safely together with the caisson in the upper area of the dock where, they point out, the gate has been standing in the dock for a long time, during which other ships had been admitted for repair. But the gate wasn’t previously surrounded by scaffoldin­g.

TNPA’s contract issued to Channel Constructi­on called for a 24hour operation working day and night shifts seven days a week to enable an on-time completion of the contract. The scope of the work includes demolition and waste disposal, structural repair, welding, modificati­on and replacemen­t of structural members and plates, design and fabricatio­n certificat­ion, commission­ing and final handover.

The contract has a R30-million price tag.

Newspapers in English

Newspapers from South Africa