The Mercury

They don’t have the required skills and knowledge to do the jobs, laments Eskom

- Siseko Njobeni

CONTRACTOR­S brought in to execute some of Eskom’s big capital expenditur­e projects did not have the necessary knowledge and skills to carry out major projects in South Africa, the power utility has said.

The poor execution of major projects, along with cost escalation­s and schedule slippages at a time when South Africa desperatel­y needed additional capacity, call into question the capability of some of the contractor­s and Eskom’s responsive­ness to the problems the utility had flagged.

Eskom has laid the blame for the delay of its Medupi power station in Lephalale, Limpopo, partly at the door of the contractor­s.

“Specialise­d welding on the boiler was of poor quality, the failure of some control and instrument­ation factory acceptance tests and substantia­lly lower than anticipate­d productivi­ty resulted in both cost and schedule movements,” Eskom said.

Business Report has seen a 2013 Pricewater­houseCoope­rs (PwC) report on welding defects at the Medupi power station. The welding problems saw Eskom issue a stop work order at the power station in March 2012.

The report partly lifts the lid on the circumstan­ces which led to the delay in the commission­ing of the power station’s first unit, Unit 6. According to Eskom, the initial synchronis­ation of the unit was November 2012. But the unit started feeding power into the grid only in March last year.

Non-compliance

The report also shows that Eskom took long to resolve problems it had identified with the boiler contract. For instance, when the PwC report was finalised in April 2013, the non-compliance report which Eskom had issued had been unresolved for three years.

“Eskom recognised from the beginning of the new-build programme that there were insufficie­nt competent engineerin­g practition­ers to execute Medupi and Kusile return-toservice units and gas projects at the same time. A strategy was formulated to contract-in large and multinatio­nal engineerin­g companies to assist Eskom.

However, the roles and responsibi­lities were not ideally defined. As a result, the decision-making and processes to be followed sometimes took too long, and in some cases resulted in the duplicatio­n of effort,” Eskom said.

As far back as January 2009, there were problems with Medupi’s boiler contract, which ESKOM on Friday signed a R6 billion loan facility from French developmen­t finance company, Agence Française de Développem­ent (AFD) for the power utility’s investment­s in the extension and reinforcem­ent of its power transmissi­on grid.

Eskom has been raising money to strengthen its transmissi­on network as it is required to accommodat­e additional capacity from renewable energy technologi­es. Last year it received a $1.34bn loan from the African Developmen­t Bank for investment in

was executed by Hitachi Power Africa, a company whose participat­ion in Eskom projects raised controvers­y because of its close links to the ANC’s investment arm, Chancellor House.

In March 2012, Eskom brought in an external assessor, Werner Kessel, to conduct a site visit at Medupi to establish the amount of work and schedule time it would take to achieve a

 ??  ?? This file photo shows a view of the constructi­on site at Medupi power station in Lephalale, Limpopo. Eskom has laid the blame for the delay in the constructi­on of Medupi partly at the door of contractor­s. Specialise­d welding defects resulted in the...
This file photo shows a view of the constructi­on site at Medupi power station in Lephalale, Limpopo. Eskom has laid the blame for the delay in the constructi­on of Medupi partly at the door of contractor­s. Specialise­d welding defects resulted in the...

Newspapers in English

Newspapers from South Africa