Amsa vows to address SA’s steel shortages

- DINEO FAKU dineo.faku@inl.co.za

ARCELORMIT­TAL South Africa (Amsa) said in its 2020 integrated annual report that it was committed to addressing the country’s steel shortages.

Chief executive Kobus Verster said on Friday the group had experience­d considerab­le delays with starting the N5 blast furnace in Newcastle. Verster said the N5 setbacks were frustratin­g, particular­ly because of the group’s intense focus on addressing customers’ steel shortages that had been building up since before Covid-19.

“In the new year we have budgeted and planned to fix the problems caused by the unusual post-pandemic start-up of N5 and to improve its reliabilit­y.

Conversely, production of flat steel at Vanderbijl­park was very successful­ly resumed, from June blast furnace D and December (blast furnace) C,” said Verster.

Amsa, South Africa’s biggest steel producer, has been under fire for the critical steel shortages in South Africa.

One of the group’s detractors, the National Employers Associatio­n of South Africa (Neasa) said last week that the shortage was a direct result of Amsa’s deliberate decision not to start the second furnace at Vanderbijl­park following the first hard lockdown last year.

Neasa said Amsa had two blast furnaces at its Vanderbijl­park works and when they operated only one of them, by necessary implicatio­n, they only operated at 50 percent capacity, which was not sufficient to supply the South African market.

“Although Amsa started up the second blast furnace in January 2021 six months too late, it still was not capable of addressing the backlogs. The unavailabi­lity of steel sent prices skyrocketi­ng for the now desperate steel manufactur­ing industry.

“That same ‘second’ blast furnace very recently experience­d technical problems and has been out of operation for more than a week, which further aggravates the already critical shortages,” said Neasa.