Sunday Times (Sri Lanka)

Fisheries harbour deals: Consultanc­y firm in hot water

Politicall­y connected company alleged to have bloated estimates to get a bigger fee Probe reveals irregulari­ties in the award of contract to Power Asia

- By Namini Wijedasa

Apolitical­ly influentia­l consultanc­y firm that inflated the estimated cost of three fisheries harbours to secure a multimilli­on rupee fee has seen its payment sliced by half after an official inquiry.

Power Asia Consultant­s has now been paid just Rs. 92 million of its total Rs. 177 million consultanc­y fee. Project officials insist that, “despite intense political pressure,” they will not fork out the rest.

In 2014, the company won a contract to conduct feasibilit­y studies and design fisheries harbours in Silawathur­a, Gurunagar and Gandara. The bid circumstan­ces are in question. The Ministry of Fisheries and Aquatic Resources Developmen­t invited a handful of companies to submit proposals. They were allotted just 12 days to do so. It was also specified that the final study must be presented within eight weeks.

“None of the other companies came forward,” said an authoritat­ive source, requesting anonymity. “Not only was there insufficie­nt time to present a serious and competitiv­e bid, a study of this nature could not be delivered in eight weeks. At minimum, it would require six to 8 months.”

Power Asia was “hurriedly” awarded the contract, the source said.

Chamath de Silva, the company’s Chairman, however, rejected allegation­s that he exploited connection­s with Chathura, the son of Rajitha Senaratne, the then-Minister of Fisheries and Aquatic Resources Developmen­t, to clinch the deal.

“We have no connection,” he protested, when contacted by the Sunday Times recently. “We are just friends.”

Industry sources say, however, that is not the practice for new companies without prior experience in similar work to be granted such consultanc­ies. According to its own website, Power Asia was only incorporat­ed in 2014.

Power Asia also lacked in-house expertise, even in part, to profession­ally undertake the study. It was usual to check a company’s average annual turnover to determine whether it matched the value of the consultanc­y award. This was not done. Until it was awarded the fisheries harbour study, the firm did not have a registered office. Auditors are now investigat­ing.

In its final report, Power Asia predicted that each harbour would cost around Rs. 6 billion to build. It then sought a massive Rs. 177 million in consultanc­y fees -- or 0.95 percent of the total estimated cost of Rs. 18 billion for three harbours. This bred suspicion that it had grossly inflated the figures to extract higher fees.

The Sunday Times received letters, including one from an official of the Ministry of Fisheries and Aquatic resources Developmen­t, saying bills of quantities (BOQ) tabulated by Power Asia for each harbour were unrealisti­c and inflated. Neverthele­ss, Kumar de Silva, the former Project Director, made an initial payment of Rs. 46 million to the company.

Following the Government change in January 2015, new Project Director Nihal Somaweera suspended payments and requested the Fisheries Harbour Corporatio­n to review the estimates. A committee studied the respective BOQs and recommende­d price reductions.

“It was establishe­d that certain items were highly overpriced,” said an official source familiar with the committee’s deliberati­ons. “Based on the report of the Fisheries Harbour Corporatio­n, the project office requested an experience­d engineer to work out the costs. Many adjustment­s were made.”

“For instance,” he continued, “the costs of dredging the Silawathur­a site were reduced to justifiabl­e levels. In all three harbours, the company quoted a very high percentage as ‘preliminar­y items’. This was cut from 35 per to 10 percent.”

The project office has also referred the BOQs to the University of Moratuwa’s Quantity Surveying Division for independen­t evaluation. Power Asia has so far been paid Rs. 92 million, with the final tranche being handed over on Friday. It is feared the company will take legal action to secure its full fee.

Industry sources argue that even the disbursed amount is far too high. “Their charges were reduced by fifty percent,” said an engineer, who did not wish to be named. “But it is fifty percent of a grossly inflated fee!” (Project officials explain they are bound by the terms of the agreement signed with Power Asia).

The sources also questioned the need for a study in the first place. “Two foreign consultant firms have already done two feasibilit­y studies along with preliminar­y designs,” said one of them. “The first, by a Danish company, placed the costs at Euros 90 million. The second, by a French company, assessed the costs at Euros 135 million.”

However, the Project Implementa­tion and Monitoring Unit (under the Ministry of Fisheries and Aquatic Resources Developmen­t) justified a third study saying the French firm had deviated substantia­lly from the estimates of the Danish company.

“The logical solution would have been to instruct the French company to provide a detailed bill of quantities (BOQ) with breakdown of rates,” said an engineer. “A qualified team could then have reviewed the submission. Instead, it was decided to commission a third study at tremendous cost to the public.”

Power Asia’s report contains extracts from the previous studies. There is no evidence of fresh investigat­ions, such as bathymetri­c or geotechnic­al surveys. Moreover, its estimates are similar to that of the French company.

The engineer said it was unusual for a contract to be awarded on a fee based on the value of a preliminar­y design. “It deviates from all standard norms in the consultanc­y industry,” he explained. “A percentage of the detailed design is paid when the design is definitive and the costs are accurately known. In a preliminar­y design, costs are just estimates. The justifiabl­e method is to agree on a lump sum fee.”

Industry experts claimed that the price of Rs. 6 billion per harbour is six to seven times the actual building cost. “The three harbours are to be developed at different scales,” the engineer said. “So the costs should vary substantia­lly from each other. Power Asia, in providing the same estimate for each, seems to have forgotten that.”

For instance, Gandara is a relatively deep harbour, extending to water depths of 8-10 metres. Gurunagar harbour is to be constructe­d inside lagoon in calm waters and does not require major breakwater­s. Only moderate shore infrastruc­ture is needed for smaller boats with inboard engines.

Engineers also agree that some excavation and dredging quantities have been “fictitious­ly increased by many times”. For example, Silawathur­a has a basin area of five hectares. Power Asia’s BOQ states the dredging volume at 490,000 cubic metres (costing Rs. 1,300 million).

“Say that 60,000 cubic metres of this is set aside for the navigation channel,” said a senior engineer. “The remaining 430,000 cubic metres of dredging will cause a harbour of 9.5 to 10 metres in depth! But all fisheries harbours in the country have average depth of between three and 3.5 metre water depths.”

 ??  ?? Views of fisheries harbour project sites in Gurunagar (left) and Silawathur­a (right)
Views of fisheries harbour project sites in Gurunagar (left) and Silawathur­a (right)
 ??  ??

Newspapers in English

Newspapers from Sri Lanka