Sunday Times (Sri Lanka)

CMC blessed the collapsed Wellawatte building twice, inquiry finds

- By Chrishanth­i Christophe­r

The report says that the sub -contractor­s had admitted that qualified people had not been involved in the Wellawatte project and that instructio­ns for steel reinforcem­ents had come through the owner. Also, no authoritie­s came into inspect or monitor the work.

The authoritie­s did not monitor or inspect the work on the Wellawatte building that collapsed, and there was no mechanism for checking the constructi­on work, the industry regulator has found. The Colombo Municipal Council had also given blanket approval for the building — twice in the span of three years.

Apart from that, qualified people were not involved in The Excellency project, there were no proper designs, no project managers, no planning, and the contractor­s were changed every now and then.

These are among a long list of findings in a report by the Constructi­on Industry Developmen­t Authority, following an investigat­ion.

The report also highlights the need to empower the regulator. The CIDA Act has not been gazetted.

The report was handed to Housing and Constructi­on Minister Sajith Premadasa last week.

CIDA’s Director and engineer Savindra Amaraseker­a, said that, according to Colombo Municipal Council requiremen­ts, buildings built for recreation­al purposes must not exceed three floors. In 2006, the owner of ‘The Excellency’ had been granted approval to build a rectangula­r structure with two basement floors, the ground floor and seven floors on top.

But it had been amended into an ‘ L’ shaped building. After that there had been an attempt to build an extension to the original building in the rear. The owner had not commission­ed qualified people to build the extension.

CIDA said there were no records of when the work started on the extension and for how long it went on. Work had been going on for sometime with intervals between. Work has been handed to different contractor­s.

While the original building (front portion) stood firm, it was the new structure that was being built that crumbled.

Investigat­ions reveal that the CMC had approved the first building in 2006 and given a second approval in 2009. There is no reason given for the second approval. However there had been a lapse of three years (2006 to 2009) between the approval and the completion of the building. The completed building was ‘L’ shaped instead of rectangula­r.

The owner has not obtained approval for the extension that collapsed, nor had he obtained a certificat­e of conformity. ‘The owner was apparently trying to make it a rectangula­r building using the original structural approval. ‘There was only a blanket approval for a rectangula­r shaped building,’ Amaraseker­a said.

According to the report, major lapses included a lack of proper designs for subsequent phases, inadequate planning and scheduling, lack of project managers, poor communicat­ions, changing of contractor­s from time to time, and the absence of collaborat­ion with technical groups, coupled with improper or no monitoring mechanism from the authoritie­s.

The two structural approvals given were by the then director of planning of the CMC. Both documents were signed by one and the same person.

Worsening the problem, the extension wing the contractor­s were working on was touching the water of the canal that runs behind the building. The CMC regulation­s require that any building running along a waterfront has to be set back 20 feet. Also, the constructi­on should have the National Building Research Organisati­on approval with regard to quality of piling used and the structure of the building.

CIDA, the building regulator, requires under its act that organisati­ons having jurisdicti­on over huge constructi­on projects (CMC and the Urban Developmen­t Authority) notify it. Also CIDA Act No. 33 of 2014 insists that ethical practices be adopted in constructi­on works of such nature using registered contractor­s.

The report says that the sub -contractor­s had admitted that qualified people had not been involved in the Wellawatte project and that instructio­ns for steel reinforcem­ents had come through the owner. Also, no authoritie­s came into inspect or monitor the work.

However, the CIDA Act, although it was passed on December 9, 2014, has not been gazetted. The draft bill is with the Legal Draftsman’s Office.

The act includes 20 regulation­s recommendi­ng the employment of qualified persons in preparatio­n of designs - including architectu­ral, structural, electrical, water supply and sewerage, designs - and services.

Emphasis is also laid on obtaining certificat­es of conformity from relevant authoritie­s for all constructi­on projects and for work to be attended to by CIDA registered contractor­s.

CIDA’s web- based Constructi­on Contractor Performanc­e Monitoring System may be viewed to check changes to the threshold limits of project values to cover all identified constructi­on work considerin­g the practical limitation­s. The present threshold value remains at Rs 10 million.

 ??  ??
 ??  ??

Newspapers in English

Newspapers from Sri Lanka