Sunday Times (Sri Lanka)

Megapolis Ministry dumps WB loan for Puttalam garbage project

- By Namini Wijedasa

The World Bank (WB) and the Ministry of Megapolis and Western Developmen­t this week split hairs over the ministry’s decision not to take WB funding for a sanitary landfill at Aruwakkalu in Puttalam.

Issues regarding the project procuremen­t process were first highlighte­d by the Sunday Times in January this year. China Harbour Engineerin­g Company Ltd (CHEC) won the US$ 100.9 million (LKR 15.64 billion) contract which includes building transfer stations at Kelaniya and Aruwakkalu and railway connectivi­ty lines. The deal was signed in December last year.

But losing bidder M/ s Kolon- HansolKECC, a joint venture from South Korea,

complained to the Procuremen­t Appeal Board ( PAB) saying CHEC had not met the mandatory criteria to be eligible for considerat­ion. It said the bidder must either have landfill design experience or submit its applicatio­n with a joint partner who had such expertise.

Kolon-Hansol-KECC also said CHEC had not provided documentar­y evidence of its eligibilit­y and qualificat­ions to perform the contract, no joint venture agreement or letter of intent to enter into such agreement, and no bid security or bid security declaratio­n. All were mandatory requiremen­ts.

The PAB found merit in the appeal and declared that both CHEC and Kolon- Hansol KECC had not fulfilled conditions in the bid document. It observed, however, that three out of five other rejected parties had met mandatory requiremen­ts but were struck off “on not fulfilling lesser critical areas such as not giving full details of personnel, equipment, subcontrac­tors and manufactur­ers, etc.”

The PAB recommende­d opening the other five financial proposals; obtaining required clarificat­ions from all bidders; and allowing the Standing Cabinet Appointed Procuremen­t Committee ( SCAPC) to negotiate with the bidders who met the essential specificat­ions “with the objective of obtaining a realistic offer, to ensure a tenderer is found within the acceptable cost range”.

Yet the Government proceeded with awarding the contract to CHEC ( after opening the financial bids of the rejected parties, as advised). The company had qualified because it submitted a letter of intent to form a consortium with the Designer, Southwest Municipal Engineerin­g Design and Research Institute of China (SMEDRIC), a spokesman maintained.

No negotiatio­ns were conducted with the failed bidders as their “overall responsive­ness was below the acceptable level”. “The PAB has the right to submit its opinion based on its own analysis,” the spokesman pointed out. “However, in the case of this procuremen­t, the responsive­ness of the bid submitted by CHEC was clearly establishe­d giving sufficient clarificat­ions.”

It has now emerged that the WB-- which had offered funding of US$115 million towards the solid waste management project--had also raised concerns.

The two sides had discussed the loan, the WB said in a statement. It was agreed that the Government would proceed with procuremen­t. The Bank would reimburse payments “so long as the procuremen­t processes followed by both GoSL and World Bank procuremen­t rules and the selected contractor met all technical, social and environmen­tal requiremen­ts."

“The GoSL considered these requiremen­ts and has decided to use its own funding to finance the urgently needed landfill contract,” the Bank also said, in response to a query from the Sunday Times. “The proposed loan was not yet submitted to the World Bank for considerat­ion and, therefore, there is no loan cancellati­on by the World Bank.”

The ministry maintained this week that the Government “has not taken any decision not to use the World Bank loan for the project”. But the sanitary landfill is being funded by the Government using consolidat­ed funds disbursed through the ministry, a spokesman also said. The project is expected to be finished by November next year.

The World Bank had flagged issues about procuremen­t, he confirmed, but indicated that it was over the opening of the financial bids of technicall­y nonqualifi­ed bidders during the procuremen­t process before award of the contract--which was done on PAB counsel.

The ministry said the WB wanted to complete all environmen­tal and social requiremen­ts before starting any operations on the ground. “However, it was an almost impossible and difficult task since the ministry had already started its initials work with determined target of completing the project within a span of 18 months,” the spokesman asserted. ( The project was originally planned for three years but expedited after the Meethotamu­lla tragedy).

This is not to say the ministry wanted to avert social and environmen­tal considerat­ions, he insisted. But these are usually fulfilled in parallel with implementa­tion. The project involves loading municipal solid waste into sealed containers to be transporte­d by rail to a sanitary landfill in Aruwakkalu.

Newspapers in English

Newspapers from Sri Lanka