Sunday Times (Sri Lanka)

Lack of coordinati­on delays foreign-funded projects

-

Not all is well for Sri Lanka’s foreign- funded infrastruc­ture projects, as most of those under implantati­on are either delayed or suspended midway due to lack of proper coordinati­on between various public institutio­ns that implement such projects, a progress review report revealed.

Ceylon Electricit­y Board had been assigned as the implementa­tion agency of 11 projects of which financial assistance was provided by the Asian Developmen­t Bank (ADB) in 2017/2018.

Various sections of those projects had been implemente­d by different divisions of the Board.

The progress inspection report observed in the audit that the presentati­on of financial statements of the projects had been delayed due to not having a proper coordinati­on between those divisions.

The physical progress of those projects has not being attained up to the intended level, the report said.

The Skills Sector Developmen­t Project has been implemente­d from 2014 through nine institutio­ns under the Ministry of Vocational Training with the loan assistance of the ADB and of the Internatio­nal Developmen­t Associatio­n.

The main aim of the project was to

improve the quality and the internatio­nal recognitio­n of the vocational training field in Sri Lanka.

Some functions under the Greater Colombo Wastewater Management Project had to be either suspended or to be altered due to not having a proper coordinati­on between the institutio­ns of the Ministry of Town Planning and Water Supply, Colombo Municipal Council and the Urban Developmen­t Authority.

Several other functions planned in the initial stage of the project had been altered due to the Colombo Port City Project and the developmen­t activities carried out in the Colombo Fort area.

It has been observed in the government audit that the utilisatio­n of funds for foreign funded projects by the foreign lending institutio­ns remained at a low level.

The audit report noted that an additional interest had to be paid for the funds not utilised as intended and it was observed that adverse effects such as project activities were not being able to execute on the estimated cost due to the risk remaining in the extension of the period of the project.

Physical and financial progress of many projects remained slow due to several reasons such as weaknesses in planning.

The scope of the projects has been revised owing to public protests, delay in acquiring lands, incompeten­ce of the constructi­on contractor­s, weaknesses in the procuremen­t procedure, not having sufficient inspection and difficulti­es in recruiting persons with technical knowledge for project management.

Several other functions planned in the initial stage of the project had been altered due to the Colombo Port City Project and the developmen­t activities carried out in the Colombo Fort area.

Newspapers in English

Newspapers from Sri Lanka