Sunday Times (Sri Lanka)

Blackout: CEB engineer says multiple tripping prevented early restoratio­n of power

CEB gives explanatio­ns but critics have more questions

- By Namini Wijedasa

The countrywid­e power failure this week lasted between six and nine hours because every time engineers attempted to rig various generators to the system, they kept tripping or disconnect­ing from the grid, a senior engineer said.

“The simple answer is that we tried every protocol we had in place but it kept tripping at some point, many times,” said Susantha Perera, Deputy General Manager (Transmissi­on Design) at the Ceylon Electricit­y Board (CEB).

The reason for why this happened is yet to be determined.

At least three separate groups -- the CEB, a committee appointed by the Power and Energy Minister, and the Public Utilities Commission of

Sri Lanka

(PUCSL) -- are looking into why all of Sri

Lanka lost power on

Monday after an electrical superinten­dent carrying out routine maintenanc­e at the Kerawalapi­tiya substation “forgot to disconnect the earth before switching the supply back on”. The committee report is expected tomorrow.

“He had attended to his maintenanc­e work which requires him to earth the bus bar,” Dr Perera said. “But he has to remove the earth before he puts the supply back. He forgot to do that.”

An electrical bus bar is defined as a conductor or a group of conductors used for collecting electric power from the incoming feeders and distributi­ng them to the outgoing feeders. It is a type of electrical “junction” in which all the incoming and outgoing electrical current meets.

The CEB says the resultant voltage surge caused the coal power plant at Norochchol­ai to trip or disconnect from the grid. This caused a cascade effect which saw other power plants also trip or disconnect from the grid as their individual protection systems became activated.

However, even in such an event, the utility should have been able to return power within two hours. But it took much longer because, while the CEB followed each of the several protocols in place to restore electricit­y, the system kept becoming unstable and the generators tripped.

Meanwhile, the CEB maintains that it was the short at the Kerawalapi­tiya substation that took Norochchol­ai off the grid but the matter is still under investigat­ion.

He had attended to his maintenanc­e work which requires him to earth the bus bar. But he has to remove the earth before he puts the supply back. He forgot to do that.”

The Ceylon Electricit­y Board’s (CEB) systems control centre (SCC) is a spanking new, Rs 3bn state-of-the art office in Kotte. Its remote terminal units collect data from different points in the grid, allowing for real time data analysis and decision-making. And it monitors 63 grid substation­s and 15 power plants.

On Monday, the room was teeming with engineers. Where there were usually three or four manning a shift, there were now 20 to 30. Some were former systems control engineers. Others were senior profession­als systems control experience, including the General Manager. But for several fraught hours, something just kept going wrong. The country was in darkness.

Careless mistake

The crisis broke earlier that day when an electrical superinten­dent carrying out routine maintenanc­e at the Kerawalapi­tiya substation “forgot to disconnect the earth from the bus bar before switching the supply back on”.

An electrical bus bar is defined as a conductor or a group of conductors used for collecting electric power from the incoming feeders and distribute them to the outgoing feeders. It is a type of electrical “junction” in which all the incoming and outgoing electrical current meets.

It was a level of careless not expected of “a person of that caliber,” a senior CEB official said. “He has been doing the same thing hundreds of time during the last five years.”

The CEB says that the resultant voltage surge caused the coal power plant at Norochchol­ai to trip or disconnect from the grid. There was then a “cascade” with other power plants also tripping or leaving the grid as their individual protection systems became automatica­lly activated. This could happen both when demand for electricit­y is higher than supply or supply is higher than demand.

That was problem enough. But the CEB then failed to reconnect the various power stations to the grid and restore electricit­y to the country. What should have taken two hours took many more. “We tried every protocol we had in place but it tripped at some point, many times,” said Susantha Perera, Deputy General Manager (Transmissi­on Design).

Black start

At the time, the CEB had to do what is called a “black start”. This means the system was dead, none of the generators were working and the transmissi­on lines were not connected. Following protocols, the engineers started up certain hydro power stations first and started energizing substation­s step-by-step.

But each time they tried to connect the load--particular­ly around Colombo where it was heavy--it tripped. That is, the generators disconnect­ed from the grid.

“We would start up Laxapana, for instance, energize one or two substation­s and try to connect the load,” Dr Perera said. “When that tripped, we would try the protocol for another generator. It would be successful to a point and then trip. To say it was frustratin­g was to put it very mildly.”

Why this kept happening is one of the issues various teams, including the CEB’s own internal inquiry, will go into. They will also look into the connection between the issue at Kerawalapi­tiya and the debacle that followed.

“As to how it happened, I don’t believe anybody knows the answer at the moment,” Dr Perera said. “You have to analyse tons and tons of data to come to a concrete conclusion. But there is nothing to hide and an independen­t committee is also working on this.”

“To put it simply, everything in the system is interconne­cted,” he continued. “When there is something faulty, or a disturbanc­e such as what happened in Kerawalapi­tiya, there is a sophistica­ted protection system in place which isolates the healthy system from the faulty part. The basic idea is to protect the generators from the surge that is coming through the system. That is what happened.”

Criticism

But did the protective systems at Norochchol­ai react too soon? It could have been that they were too sensitive, Dr Perera said, and detected the fault from far away. It was the tripping of the coal power plant--Unit 1 first, followed by the other 2--that caused the cascade, not the

Kerawalapi­tiya fault.

Critics like Vidhura Ralapanawe, who closely analyses developmen­ts in the power sector, question how the whole system went under so fast. The Kerawalapi­tiya grid substation accounted for only six percent of the load in the system, he said. The normal rule of thumb is that up to 10 percent of sudden loss can be tolerated in the grid system.

“In a properly coordinate­d grid system, where the protection co-ordination is done accurately, the protection system works only to get the faulty area isolated by leaving the other healthy areas in operation,” Dr Ralapanawe pointed out. “The whole idea of having protection systems working at different levels is to isolate the unhealthy part of the system in order to protect the healthy part getting affected.”

“For an example, if you have a fault in your bedroom air-conditione­r, then only the circuit breaker supplying power to

your bed room area should trip,” he said. Not the whole house. And, of course, that fault should not trip the transforme­r feeder supplying your housing area.”

Electrical superinten­dent

Dr Ralapanawe also questioned how the electrical superinten­dent attended to the maintenanc­e work at Kerawalapi­tiya without the supervisio­n of an engineer.

“It may be true that the physical work of earthing has been done by an electrical superinten­dent but this activity involves a very high- level, knowledgea­ble skilled engineer to authorize the work and also to carry out the work,” he said. “If so, who is CEB trying to defend by putting the superinten­dent in front?”

He asked whether CEB had standard operating procedure for such maintenanc­e work and which CEB officer must approve the work. Had this procedure been followed and required clearance obtained? And is approval needed from the SCC?

“It is strange and not acceptable at all if this kind of protection and interlock bypass has not been done under the supervisio­n of a senior protection engineer of the CEB,” he insisted.

“You can argue either way, whether there should have been a supervisor or not,” Dr Perera replied. “Fact is he has been doing this work and followed the required permit process each time. An electrical superinten­dent in the CEB is a highly technical person with almost the same training as engineers.”

Power cuts

With Norochchol­ai off the grid, the CEB introduced rolling power cuts that ended on Friday when Unit 1 was reconnecte­d to the grid. Unit 2 and 3 were expected to follow after they cooled down enough to be restarted.

 ??  ?? Operation restoratio­n of power: Scene at Norochchol­ai power plant on Friday. Pic by Hiran Priyankara Jayasekera
Operation restoratio­n of power: Scene at Norochchol­ai power plant on Friday. Pic by Hiran Priyankara Jayasekera
 ??  ?? Small scale busineses were hit badly by the breakdown on Monday. Pix by Lahiru Harshana and Indika Handuwala
Small scale busineses were hit badly by the breakdown on Monday. Pix by Lahiru Harshana and Indika Handuwala
 ??  ??

Newspapers in English

Newspapers from Sri Lanka